Verify the phase to phase line voltages of both the
normal and emergency power sources are the same
and that they match rated voltage as indicated on
the ATSBI equipment ratings label.

SEVERE EQUIPMENT DAMAGE CAN RESULT IF
UNIT IS NOT APPLIED TO PROPER VOLTAGE.

DO NOT ENERGIZE EQUIPMENT IS SUPPLY
VOLTAGES DO NOT MATCH EQUIPMENT
RATINGS LABEL. CONTACT THE FACTORY FOR
FIELD VOLTAGE RATING MODIFICATION
INSTRUCTIONS.

FUNCTIONAL TESTING

Following the operational instructions label on the
enclosure front, proceed to place the equipment in
the Normal Bypass mode. Set the enclosure
mounted auto/test switch to the auto position.

YOU ARE READY TO ENERGIZE EQUIPMENT.
VOLTAGES WILL  EXIST WITHIN THE  ENCLOSURE
CAPABLE OF CAUSING SEVERE PERSONAL
INJURY OR DEATH.

USE EXTREME CAUTION TO AVOID CONTACT
WITH ENERGIZED EQUIPMENT.

ENERGIZING NORMAL SOURCE

With the main switch in the Normal Bypass position,
apply normal source power to the equipment by
closing the normal upstream breaker or switch
supplying the ATSBI switch on the normal side.

NOTE: The load terminals of the unit will now be
energized. If it is undesirable to energize connected
load equipment during the functional tests,
measures should be taken to isolate such loads by
opening an appropriate downstream breakers.

The ATS power panel may cycle to close to the
normal position if not already in normal. This DOES 

NOT indicate a presence of voltage on the ATS
power panel since the ATS logic panel senses on
the line side of the Bypass switch.
Utilizing a voltmetre measure phase-to-phase-to-
neutral voltages across the normal bypass line
terminals to ensure normal voltage is correct.

CONTACT WITH ENERGIZED COMPONENTS CAN
CAUSE ELECTRICAL SHOCK CAPABLE OF
PRODUCING SEVERE PERSONAL INJURY OR
DEATH. USE EXTREME CAUTION TO AVOID
CONTACT WITH ENERGIZED COMPONENTS
WHEN USING A METER FOR VOLTAGE CHECKS.

The following status indicator lights mounted on
device panels of both the Bypass (upper) enclosure
panel and the ATS (lower) enclosure door should be
lit.

1.

Normal Bypass Energized

2.  Transfer Switch Isolated
3. Normal 

Source 

Available

4. Load Energized
5. Normal Position Energized

Refer to status indicator lights section for a
complete operational description of all supplied pilot
lights.

ENERGIZING EMERGENCY SOURCE

Following the operational instructions label on the
enclosure front, proceed to place the equipment in
the Emergency Bypass Mode by opening the
Normal Bypass Switch and closing the Emergency
Bypass Switch.

With the switch in the Emergency Bypass position,
manually start the engine generator (if applicable) at
the set utilizing the generator selector switch. Apply
Emergency source power to the equipment by
closing the generator breaker ahead of the ATSBI
Switch on the Emergency side.

NOTE: The ATS Power Panel should remain
connected (closed) on the Normal Source.

9

DANGER

DANGER

CAUTION

I.L. 16913A

Summary of Contents for Cutler-Hammer BIHI

Page 1: ...IN INTERLOCKS AND SAFETY FEATURES INTENDED TO PROVIDE SAFE AND PROPER OPERATING SEQUENCES TO PROTECT PERSONNEL ASSOCIATED WITH THE INSTALLATION OPERATION AND MAINTENANCE OF THIS EQUIPMENT THE FOLLOWI...

Page 2: ...ontacting the factory for technical support A ratings nameplate will also be affixed to the switch identifying the withstand interrupting and closing ratings for which the unit is intended DO NOT APPL...

Page 3: ...ency bypass switches are provided to permit bypass to either power source but both bypass switches are interlocked with the isolation switch to positively prevent inadvertent paralleling of sources IN...

Page 4: ...Effective July 2007 3 I L 16913A Fig 2 Note For bottom entry add 14 to depth of unit...

Page 5: ...4 24 610 Single Phase Only DIMENSIONS INCHES MM BYPASS ISOLATION ATS 2 3 POLE DIMENSIONS INCHES MM BYPASS ISOLATION ATS 4 POLE Max Max Switch CSA Amps Volts Frame Bypass Frame A B C D E F G H I J 150...

Page 6: ...or ringing of the conductor strands Prepare stripped conductor termination end by cleaning with a wire brush If aluminum conductors are used apply an appropriate joint compound to the clean conductor...

Page 7: ...ition Connect the engine start wires to the RED terminal blocks marked 51A and 52A A contact closes between these terminal blocks when an engine start signal is provided by either the ATS or Bypass lo...

Page 8: ...Effective July 2007 7 Fig 3 I L 16913A...

Page 9: ...Effective July 2007 Supercedes I L 16913 dated February 1991 8 I L 16913A Fig 3...

Page 10: ...position if not already in normal This DOES NOT indicate a presence of voltage on the ATS power panel since the ATS logic panel senses on the line side of the Bypass switch Utilizing a voltmetre meas...

Page 11: ...osition the Generator control selector switch to the auto start position Additional functional load transfer tests may be desirable including automatic engine start operation See ATS Controller Manual...

Page 12: ...a downstream short circuit condition the ATS logic will engage the Transfer Mechanism to electrically reset the automatically opened switch If optional overcurrent protection option 16 17 or 37 is pro...