Position first completed 4x4
post into the lowest corner of
the ground support base (as
per you landscape). Than level
both sides.
NOTE:
Notice the position of
post is actually on the outside
of the base. Also the 2x4 teak
is facing inside of base.
NOTE:
The “O” mark is at the
top.
After leveling, fasten 4x4 post to ground
support base using 4 - 3” lags (as shown
in photo).
First post completed (as shown
in photo).
Using first post as a guide place level on PT246 floor teak mounted on post. Dig down second post until
level with first post. Again fasten with 4 - 3” lags in holes provided. Continue this process until all 4 post
are fastened.
NOTE:
Make sure the “O” is always on the top of post and 2x4 teak is facing inside of clubhouse.
NOTE: If installing on
unlevel ground place first
post in lowest corner of
ground support base and
dig the remaining 3 posts
in ground as needed to
bring level with first post.
P
O
S
T
P
O
S
T
PT246
Unlevel Ground
Level Floor Supports
O
O
O
O
O
O
O
O
Dream FLOOR Assembly Setup #4