In-ground Motion Assist 360 drive and speed control
Remote control enclosure
Chapter 12
12.4 Orientation of in-ground container in pit – building interface
12.4.1 In-ground container orientation in pit.
NOTICE
Joint between container lids must be parallel
with building interface.
12.4.2 Building conduit to container conduit adapter
positioning.
To meet Para. 12.4.1 requirement, container can be
placed in one of four positions in pit for interfacing
container conduit adapter to building conduit.
(Fig. 12.4.3).
12.4.3 Determining container orientation - container
conduit adapter entrance location.
• Reference Para. 12.6 to determine container
orientation for building conduit interface to
1 1/2" DC conduit adapter.
TIPS AND RECOMMENDATIONS
Orientation of container DC conduit adapter
in pit must be determined before locating
position of through-wall pipe fitting for
container drain (Reference Para. 12.6).
Fig. 12.4.1 Container lids parallel to building interface
Building
interface
Building
interface
In-ground
container
assembly
Container
lid
1
1
1
1
Fig. 12.4.3 Container conduit adapter orientations in pit
1
Container lid
Fig. 12.4.2 In-ground container orientation example
1
DC conduit adapter
Fig. 12.4.4 Container conduit adapter - orientation in pit
example
1
DC conduit adapter
2
Container
lid
3
Leveling plate
Pourstone
Concrete
1
2
3
2
1 1/2" conduit
adapter, DC wiring
1
1
2