21
BIOCLASS iC 150
4.5
Start-up
To ensure the
validity of the guarantee
is effective, the boiler must be started up by
personnel
authorised by DOMUSA TEKNIK
. Before beginning the start-up process, the following must be
complied with:
•
The boiler must be plugged in to the mains.
•
The installation must be filled with water (the pressure must be between 1 and 1.5 bar).
•
The reserve tank must be filled with fuel.
•
The start-up sequence is as follows:
•
Check that the flue is correctly installed as it must include a condensation inspection plate
and a draught stabiliser.
•
Check the reserve tank and the fuel feeder auger are correctly installed.
The feed auger
must be calibrated for correct boiler functioning
(See “Calibrating the feed auger”)
.
Check that the type of fuel is suitable (for wooden pellets it must be
ENplus
A1
,
DIN PLUS
or equivalent).
•
If the installation has flow and return valves, check they are open.
4.6
Installation hand-over
After the initial start-up, the Technical Assistance Service will explain to the user how the boiler
functions, making any observations they consider relevant.
The installer is responsible for clearly explaining to the user the functioning of any control or regulation
device forming part of the installation but not supplied with the boiler.
On delivery of the boiler, the user receives the following documents:
•
The installation and operating manual of the boiler
•
Analysis of the combustion performed during start-up.
•
The boiler start-up sheet
Summary of Contents for BIOCLASS iC 150
Page 1: ...BIOCLASS iC 150 Biomass boiler EN INSTALLATION AND OPERATING INSTRUCTIONS ...
Page 2: ......
Page 15: ...15 BIOCLASS iC 150 ...
Page 64: ...EN 64 BIOCLASS iC 150 23 CONNECTIONS DIAGRAM 23 1 Boiler ...
Page 68: ...EN 68 BIOCLASS iC 150 ...
Page 77: ...77 BIOCLASS iC 150 NOTES ...
Page 78: ...EN 78 BIOCLASS iC 150 NOTES ...
Page 79: ...79 BIOCLASS iC 150 NOTES ...