PR95 Operator’s Manual
Burst Pipe - 49
Pull Pipe
CMW
8.
Thread one rod onto rod in bursting unit.
9.
Remove rod makeup device.
10. Push bursting unit back slightly to remove pulling brace.
11. Move burster back in pit and position extension frame between between pipe burster and existing pipe.
12. Put bursting unit in pull mode and pull towing system into extension frame.
13. Remove extension frame.
14. Disconnect and remove towing system.
15. Remove bursting unit from pit.
16. Connect both ends of new pipe to existing pipe to complete job.
IMPORTANT:
Ensure extension frame is level and centered. Pull bursting unit forward until it is
firmly against extension frame.
Summary of Contents for PR95
Page 1: ...PR95 Operator s Manual 053 1102 Issue 1 0 CMW...
Page 19: ...Safety 18 PR95 Operator s Manual Emergency Procedures CMW...
Page 39: ...Prepare 38 PR95 Operator s Manual Check Supplies and Prepare Equipment CMW...
Page 51: ...Burst Pipe 50 PR95 Operator s Manual Pull Pipe CMW...
Page 57: ...Systems and Equipment 56 PR95 Operator s Manual Accessory Kit CMW...
Page 92: ......
Page 93: ......
Page 94: ...PR95 Operator s Manual Service Record 93 CMW Service Record Service Performed Date Hours...
Page 95: ...Service Record 94 PR95 Operator s Manual CMW Service Performed Date Hours...