RAID Array 410 to 450 Upgrade
6–10
EK–SM410–UP. A01
3. With a small blade screwdriver, loosen the captive screws on the trilink connector
(see Figure 6–2) and remove the trilink from the front of the controller. Do not
remove the cable or terminator from the trilink or you will interrupt the host SCSI
bus. You will have to work around any SCSI cable or terminator connections when
removing the trilink.
Figure 6–2 Trilink Connector
4. Remove the maintenance terminal cable (if attached).
5. Loosen the four mounting screws (refer to Figure 6–3) on each side of the front panel
with a medium blade screwdriver.
Figure 6–3 RAID Array 410 Controller Panel