4.

Connect a section of pipe and extend
up through the hole.

Note:

 If an offset is needed to avoid

obstructions, you must support the vent
pipe every 3 feet. Use wall straps for
this purpose (see Figure 24). Whenever
possible, use 45° elbows instead of 90°
elbows. The 45° elbow offers less re-
striction to the flow of the flue gases
and intake air.

5.

Place the flashing over the pipe
section(s) extending through the roof.
Secure the base of the flashing to the
roof and framing with roofing nails. Be
sure roofing material overlaps the top
edge of the flashing as shown in Figure
24. There must be a 1" clearance from
the vent pipe to combustible materials.

6.

Continue to add pipe sections until the
height of the vent cap meets the mini-
mum building code requirements de-
scribed in Figure 13 on page 6.

 Note

:

You must increase vent height for steep
roof pitches. Nearby trees, adjoining
rooflines, steep pitched roofs, and other
similar factors may cause poor draft or
down-drafting in high winds. Increasing
the vent height may solve this problem.

7.

Twist-lock the vent cap onto the last
section of vent pipe and seal with high
temperature silicone sealant as speci-
fied in the second warning statement
on page 7.

Note:

 If the vent pipe passes through any

occupied areas above the first floor, including
storage spaces and closets, you must enclose
pipe. You may frame and sheetrock the enclo-
sure with standard construction material. Make
sure and meet the minimum allowable clear-
ances to combustibles. Do not fill any of the
required air spaces with insulation.

Cathedral Ceiling Installation

1.

Remove shingles or other roof cover-
ing as necessary to cut the rectangular
hole for the support box. Mark the out-
line of the cathedral ceiling support box
on the roof sheathing using the locat-
ing hole as a center point.

2.

Cut the hole 1/8" larger than the sup-
port box outline (see Figure 26, page 13).

1.

Determine the route your vertical vent-
ing will take. If ceiling joists, roof
rafters, or other framing will obstruct
the venting system, consider an offset
(see Figure 24) to avoid cutting
loadbearing members. 

Note:

 Pay spe-

cial attention to these installation in-
structions for required clearances (air
space) to combustibles when passing
through ceilings, walls, roofs, enclo-
sures, attic rafters, etc. Do not pack air
spaces with insulation. Also note maxi-
mum vertical rise of the venting sys-
tem and any maximum horizontal off-
set limitations. Offsets must fall within
the parameters shown in Figure 13 on
page 6.

2.

Set the fireplace in desired location.
Drop a plumb line down from the ceil-
ing to the position of the fireplace exit
flue. Mark the center point where the
vent will penetrate the ceiling. Drill a
small locating hole at this point.

Drop a plumb line from the inside of
the roof to the locating hole in the ceil-
ing. Mark the center point where the
vent will penetrate the roof. Drill a
small locating hole at this point.

Flat Ceiling Installation

1.

Cut a 10" square hole in the ceiling us-
ing the locating hole as a center point.
The opening should be framed to
10"x10" (254mm x 254mm) inside di-
mensions, as shown in Figure 17 on
page 9 using framing lumber the same
size as the ceiling joists. If the area
above the ceiling is an insulated ceil-
ing or a room, nail firestop from the
top side. This prevents loose insulation
from falling into the required clearance
space. Otherwise, install firestop below
the framed hole. The firestop should be
installed with no less than three nails
per side (see Figure 25).

2.

Assemble the desired lengths of pipe
and elbows necessary to reach from the
fireplace flue up through the firestop.
All connections must be sealed with
high temperature silicone sealant as
specified in the second warning state-
ment on page 7. Be sure all pipe and
elbow connections are fully twist-
locked (see Figure 16, page 9).

3.

Cut a hole in the roof using the locating
hole as a center point. (Cover any ex-
posed open vent pipes before cutting
hole in roof.) The 10"x10" hole must
be measured on the horizontal; actual
length may be larger depending on the
pitch of the roof. There must be a 1"
clearance from the vent pipe to combus-
tible materials. Frame the opening as
shown in Figure 17 on page 9.

VENTING
INSTALLATION

Continued

Figure 24 - Offset with Wall Strap and 45°

45° Elbow

Wall Strap

Roof
Flashing

Ceiling Firestop

Figure 25 - Installing Firestop

If area above is not a room, install
firestop below framed hole.

If area above is a room, install firestop
above framed hole.

INSTALLATION FOR
VERTICAL TERMINATION

NOTICE: Use rigid pipe only. Flex
venting is not to be used with a
vertical termination.

Summary of Contents for Vanguard EVDDVF36PN

Page 1: ...gas supplier s instructions If you cannot reach your gas supplier call the fire department Installation and service must be performed by a qualified installer service agency or the gas supplier SAVE...

Page 2: ...d Back of Surround Figure 2 EVDDVF36STN See Thru Dimensions Left Side Surround Right Side Surround Rating Plate Location Left Side Surround Right Side Surround GLOSSARY OF TERMS Chase A box like enclo...

Page 3: ...gas approved for use in this gas appliance NOTICE Check local building codes for area requirements be fore installing this appliance This appliance when installed must be elec trically grounded in ac...

Page 4: ...ock re quired air spaces with insula tion or any other material Do not obstruct the effective opening of the appliance with any type of facing material MANTEL CLEARANCES Woodwork such as wood trims ma...

Page 5: ...ting terminals into a wall or siding If installing on vinyl siding a vinyl sid ing standoff must be used see Figure 19 page 9 Install horizontal venting with a 1 4 rise for every 12 of run toward the...

Page 6: ...aved side walk or a paved driveway located on public property 84 inches 2133mm minimum M clearance under veranda porch deck 12 inches 305mm minimum N clearance above a roof shall extend a minimum of 2...

Page 7: ...t is important to select the proper length of vent pipe for the type of termination you choose It is also important to note the wall thickness For Horizontal Termination Select the amount of vertical...

Page 8: ...the appliance adaptor with pipe seams oriented towards the wall or floor Twist lock Procedure The female ends of the pipes and fittings have four locking lugs indentations These lugs will slide strai...

Page 9: ...of the vent cap Position the vent cap in the center of the 7 1 2 or 10 hole on the exterior wall with the arrow on the vent cap pointing up Insure proper clearance of 1 to combustibles is maintained...

Page 10: ...al V and Horizontal H maxi mums and minimums The same amounts apply for flexible venting FGFVK Vent Kit Shown Horizontal Termination Configurations Figures 21 through 23 show different con figurations...

Page 11: ...90 Elbows Vertical V Horizontal H1 Horizontal H2 5 min 4 max 6 min 8 max 7 min 10 max 8 min 15 max 20 max 20 max Figure 23 Horizontal Termination Configuration for Rigid Venting Using Two 90 Elbows w...

Page 12: ...ances air space to combustibles when passing through ceilings walls roofs enclo sures attic rafters etc Do not pack air spaces with insulation Also note maxi mum vertical rise of the venting sys tem a...

Page 13: ...ort box vertically and horizontally using a level Temporarily tack the support box in place through the inside walls and into the roof sheathing 4 Using tin snips cut the supportbox from the top corne...

Page 14: ...tion With No Horizontal Run VENTING INSTALLATION Continued Venting with Two 90 Elbows Vertical V1 Horizontal H 5 min 6 max 6 min 12 max 7 min 18 max 8 min 20 max Note Vertical V1 Vertical V2 20 max Fi...

Page 15: ...shing RTV Silicone Vertical Termination and 26 screws D1000 7 x 12 Galvanized Coaxial Pipe 6 pcs D1010 7 x 24 Galvanized Coaxial Pipe 6 pcs D1020 7 x 48 Galvanized Coaxial Pipe 6 pcs D1030 7 Adjustabl...

Page 16: ...he blower system will not flow properly WARNING Disconnect all electrical power to the fireplace Be careful of burrs and sharp edges BLOWER SPEED CONTROL INSTALLATION 1 Place speed control switch asse...

Page 17: ...em at test pressures equal to or less than 1 2 psig 3 5 kPa 1 Install a sediment trap between the in coming gas line and the gas control valve see Figure 40 The sediment trap should extend down the ce...

Page 18: ...to prevent damage to glass or refractory 1 Remove top and bottom louvers by si multaneously pulling both top end spring latches towards the center of the applianceuntiltheyaredisengagedfrom locating...

Page 19: ...d during shipping and han dling If this is the case some minor adjust ments may be necessary and should be done by a qualified technician To access the elec trode the glass door must be opened The pro...

Page 20: ...ng ignition Young children should be carefully supervised when they are in the same room as the appliance WARNING Have a qualified agency periodically inspect the vent system at the start of each heat...

Page 21: ...tes to clear out any gas Then smell for gas including near the floor If you smell gas STOP Follow B in the safety in formation in column one If you don t smell gas go to the next step 7 Turnequipments...

Page 22: ...iginalreplacementpart s call DESA International s Technical Ser vice Department at 1 800 323 5190 for re ferral information When calling DESA International have ready your name your address model and...

Page 23: ...Replace control valve see Replacement Parts page 27 5 Tighten wires or replace electrode 6 Check that the main power is on and that all wire connections are made correctly to the ignition module see W...

Page 24: ...oved from line Have gas line checked by local pro pane LP gas company 2 Clean burner or replace burner orifice 1 Adjust the log set so that the flame does not excessively impinge on it 2 Inspect the o...

Page 25: ...ss too loose and air tight gasket leaks in corners after usage 6 Improper vent cap installation 1 Gas leak See Warning statement above 1 Improper log placement 2 Air holes at burner inlet blocked 3 Bu...

Page 26: ...overplate andmillivoltwires are supplied with the appliance If wires need replacing use proper gauge Millivolt Wires Wall Switch and Cover Plate ORIFICE Natural 105890 01 27224 REPLACEMENT PARTS A A B...

Page 27: ...PARTS Continued Front Bottom Left Right Bottom Front Used for See Thru Only GRATE 105889 01 11184 DOOR ASSEMBLY Tempered 106923 01 27200 LOUVER KIT Black 105904 01 01627 END LOUVER KIT Peninsula Only...

Page 28: ...l be the responsibility of the owner TO THE FULL EXTENT ALLOWED BY THE LAW OF THE JURISDICTION THAT GOVERNS THE SALE OF THE PRODUCT THIS EXPRESS WARRANTY EXCLUDES ANY AND ALL OTHER EXPRESSED WARRANTIE...

Reviews: