DIRECT-VENT PROPANE/LP GAS HEATER

DYNAVENT

®

 WARNING: Never use an open

flame to check for a leak. Apply a
mixture of liquid soap and water
to all joints. Bubbles forming show
a leak. Correct all leaks at once.

Connecting Furnace to Gas
Supply at Rear of Furnace

1.

Remove the two screws in back of fur-
nace cabinet located by the exhaust
vent(s) (see Figures 9 and 10).

2.

Remove two screws on front lower
flange that attach furnace flange to fur-
nace cabinet flange (see Figure 11).

Note: 

40,000 BTU/Hr model has a bot-

tom shield (see parts list, page 22, for
location). Removing two screws will
detach bottom shield.

3.

Slide furnace out of furnace cabinet.

4.

Locate gas inlet pipe on lower, right
front of furnace.

5.

40,000 BTU/Hr Model Only:

 Remove

screw holding gas inlet pipe clamp to
furnace.

6.

Disconnect gas inlet pipe from 3/8"
manifold elbow. Turn gas inlet pipe
counter-clockwise to disconnect (see
Figure 12).

7.

Rotate the 3/8" manifold elbow 90

°

 so

the opening is pointing downward (see
Figure 12).

8.

Locate knockout plug in furnace cabi-
net. Knockout plug is in lower left rear
of furnace cabinet (as viewed from rear,
see Figure 13). Remove knockout plug.

9.

Slide furnace back into furnace cabi-
net. Make sure exhaust tube gaskets are
in place. Make sure exhaust and intake
vent tubes extend into vent caps on
back of cabinet. Replace two screws by
exhaust vent(s) removed in step 1.

10.

25,000 BTU/Hr Model:

 Replace two

screws removed in step 2. Attach fur-
nace flange and furnace cabinet lower
flange together.

40,000 BTU/Hr Model:

 Place bottom

shield back in place. Replace two
screws removed in step 2. Attach bot-
tom shield, furnace flange, and furnace
cabinet lower flange together.

INSTALLATION

(Continued)

11. Run 3/8" pipe or nipple through knock-

out hole. Connect 3/8" pipe or nipple
to manifold elbow (see Figure 14). See
Providing Gas Piping to Furnace,
pages 9 and 10 for correct gas pipe in-
stallation.

12. Check connections for gas leak.

13. Caulk around pipe or nipple. This pre-

vents cold air entering knockout hole.

Figure 9 - Locations of Screws in Back of
Furnace Cabinet (25,000 BTU/Hr Model)

Figure 10 - Locations of Screws in Back
of Furnace Cabinet (40,000 BTU/Hr Model)

Figure 11 - Removing Screws on Lower
Flange (40,000 BTU/Hr Model Shown)

Furnace
Flange

Furnace
Cabinet
Flange

Figure 14 - Inserting Pipe through
Knockout Hole

Figure 13 - Location of Knockout Plug

Knockout Plug

Figure 12 - Disconnecting Gas Inlet Pipe
(40,000 BTU/Hr Model Shown)

Remove Screw,
40,000 BTU/Hr
Model Only

Gas Inlet
Pipe

Manifold Elbow

3/8" NPT

Summary of Contents for DYNAVENT DNV25PB

Page 1: ...NING Improperin stallation adjustment alteration service or maintenance can cause injury or property dam age Refertothismanual for correct installation and operational proce dures Forassistanceor addi...

Page 2: ...LP gas is odor less An odor making agent is added to pro pane LP gas The odor helps you detect a propane LPgasleak However theodoradded to propane LP gas can fade Propane LP gas may be present even t...

Page 3: ...For purposes of input adjustment SPECIFICATIONS Install and use furnace with care Follow all localcodes Intheabsenceoflocalcodes use the latest edition of the following National Fuel Gas Code ANS Z223...

Page 4: ...installing thermostat in a wall make sure there are no pipes or wiring in the hollow wallabovethefurnace Thethermostatwires will pass through this wall from the attic Mounting hardware needed to moun...

Page 5: ...000 BTU Hr Model Use a proper sized drill bit Drill holes through wall and into studs at marked locations 40 000 BTU Hr Model Use a proper sized drill bit On wall stud side of opening drill holes thro...

Page 6: ...else that would interfere with install ing thermostat Do not mount thermo stat to stud If there are any obstruc tions choose a new location 3 Provide two 18 gauge insulated stranded wires for the the...

Page 7: ...t Wires to Thermostat Wall Anchors CAUTION Use only new black iron or steel pipe Copper tubing may be acceptable in cer tain areas Check local codes Use pipe large enough in diam eter to allow proper...

Page 8: ...de furnace back into furnace cabi net Make sure exhaust tube gaskets are in place Make sure exhaust and intake vent tubes extend into vent caps on back of cabinet Replace two screws by exhaust vent s...

Page 9: ...0 BTU Hr 15 000 BTU Hr for other gas appliances 55 000 BTU Hr total 55 000 2500 22 Locate 22 or higher on chart below According to the chart below you should use 40 feet or less of 3 8 pipe 125 feet o...

Page 10: ...5 CAUTION Usepipejointseal ant that is resistant to liquid pe troleum LP gas Slab Floor Installation Equipment Shutoff Valve Test Gauge Connection To Gas Supply 3 Min Sediment Trap Gas Piping Entering...

Page 11: ...0 cycle grounded outlet at furnace location 2 The furnace has a three pronged grounded plug Use only a grounded three prong outlet IMPORTANT Some local codes require rigid or semi rigid conduit or met...

Page 12: ...Do not try to light the burner by hand 8 Plug in furnace 9 Set thermostat to desired setting If thermostat is set above room tem perature the blower will come on 10 Allow approximately 45 seconds for...

Page 13: ...forces the combus tion products out of the exhaust tube s The Combustion air blower is sealed so that air does not pass between it and the circulating room air blower 3 When the blower motor reaches...

Page 14: ...r mixture Wipe cabinet and front cover to remove dust Use a vacuum cleaner to remove dust from front cover louvers EXHAUST AND INTAKE VENTS Make sure the exhaust and intake vents are not blocked The i...

Page 15: ...okay check for defective motor 5 Be sure the microswitch is sailing in far enough to open the solenoid valve and to energize the ignition control If the switch is not sailing in clean any dust or dir...

Page 16: ...t it WARNINGS Never connect unit or ignition circuit to 230 volts Never operate unit with glo bar touching burner or any other ground Damage to ignition control will occur Be sure sensor probe never t...

Page 17: ...bar broken 2 A Check for voltage 24 volts A C at valve 40 seconds after glo bar begins to glow If voltage present but valve not opening replace valve B If no voltage at valve check brown wire at igni...

Page 18: ...Be sure probe is positioned in the burner flame and glowing cherry red Check wire and wire connections at probe and ignition control B If wire and wire connections okay check for voltage across brown...

Page 19: ...hite Open WIRING DIAGRAMS Figure 21 Wiring Diagram 40 000 BTU Hr Model Figure 20 Wiring Diagram 25 000 BTU Hr Model Note Use only original replacement parts Thiswillprotectyourwarrantycoveragefor part...

Page 20: ...41 www portableheaterparts com sales portableheaterparts com techservice portableheaterparts com F B D 1349 Adams Street Bowling Green KY 42103 3414 1 800 654 8534 270 846 1199 Fax 1 800 846 0090 fran...

Page 21: ...1244 Operating Instructions Decal English 1 191246 Operating Instructions Decal French 1 531010 Warning Decal 1 191262 Nameplate 1 Parts available not shown You must order nameplate and operating inst...

Page 22: ...8 x 3 8 2 3 191241 Front Cover Trim 1 4 030642 Front Cover Assembly 1 5 100896 Cabinet Assembly 1 6 070511 Cabinet Insulation right and left sides 1 7 120158 Screw 8 x 3 8 2 8 160912 Thermostat inclu...

Page 23: ...44 Terminal Block 1 10 121224 Screw 10 x 3 4 2 11 070487 Gasket 1 12 231143 Transformer Assembly 1 13 121252 Screw 10 x 3 8 6 14 020983 Combustion Chamber Heat Shield Assembly 1 15 070606 Heat Shield...

Page 24: ...Terminals 1 13 070607 Heat Shield Gasket 1 14 020982 Combustion Chamber Heat Shield Assembly 1 15 061663 Wire Clamp 2 16 121252 Screw 10 x 3 8 12 17 230560 Limit Switch 1 KEY PART NO NUMBER DESCRIPTIO...

Page 25: ...3 4 5 6 7 8 9 10 11 12 KEY PART NO NUMBER DESCRIPTION QTY 1 120717 Hex Nut 10 24 2 2 121459 Screw 10 24 x 1 2 2 3 010701 Burner Assembly 1 4 180215 Main Burner Orifice 1 5 121388 Screw 10 x 1 2 4 6 07...

Page 26: ...PART NO NUMBER DESCRIPTION QTY 1 120717 Hex Nut 10 24 4 2 010621 Left Burner Assembly 1 3 010623 Right Burner Assembly 1 4 070591 Manifold Gasket 1 5 171167 Manifold Assembly 1 6 180188 Main Burner Or...

Page 27: ...oom air 1 8 121421 Hex Lock Nut 10 24 3 9 050751 Crossover Tube 1 10 121388 Screw 10 x 1 2 4 11 070385 Crossover Tube Gasket 2 12 121227 Screw 10 24 x 1 2 2 13 070362 Universal Bushing 1 14 231231 Cap...

Page 28: ...ombustion Air Cover Assy 1 12 121388 Screw 10 x 1 2 3 13 070420 Combustion Air Crossover Gasket 1 14 390318 Combustion Air and Motor Cover Assembly 1 KEY PART NO NUMBER DESCRIPTION QTY 15 121227 Screw...

Page 29: ...___________________ _______________________________________________________________________________________________ ____________________________________________________________________________________...

Page 30: ...lity of the owner TO THE FULL EXTENT ALLOWED BY THE LAW OF THE JURISDICTION THAT GOVERNS THE SALE OF THE PRODUCT THIS EXPRESS WARRANTY EXCLUDES ANY AND ALL OTHER EXPRESSED WARRANTIES AND LIMITS THE DU...

Reviews: