5.
MAINTENANCE SECTION
Warning!
Special vacuum maintenance must be carried out solely by specialised technicians
authorised by the DEPURECO dealer.
5.1
Informative notes
This section describes the checks and routine maintenance operations required to ensure proper vacuum
operation.
Maximum reliability and minimum maintenance costs are the result of a planned maintenance and inspection
schedule carefully followed throughout the entire lifespan of the vacuum.
Observe the set maintenance intervals and schedule the interventions according to specific requirements in
relation with the vacuum production cycle.
Always use tools that are in perfect condition and that are specifically intended for the operation to be carried
out; the use of inadequate or inefficient tools may cause serious damage.
Any other intervention required to remove faults or malfunctions must be expressly authorised by the
manufacturer.
In these cases always communicate vacuum cleaner identification data – see § 1.4 of this manual.
For significant repairs, refer to the authorised dealer, whose specialised personnel has the technological
expertise in the original factory build and is always available for prompt interventions.
For user maintenance operations, the vacuum must be disassembled, cleaned and maintained, where
possible, in such a way as to prevent hazards to the maintenance personnel and to third parties. Suitable
precautionary measures include decontamination before dismantling, measures for filtered forced ventilation
of the room where the appliance is disassembled, cleaning of the maintenance area and suitable personal
protection equipment.
At least once every three months (or more frequently, according to the operating cycle and the conditions of
use), the manufacturer or a qualified technician must check the filters, ensuring that they are not damaged;
and ensuring proper operation of the control devices.
Should maintenance operations or repairs be carried out, all contaminated objects must be adequately
cleaned, placed in waterproof bags and disposed of in compliance with the regulations in force.
Summary of Contents for RAM 1000
Page 1: ...R A M2 8 0 R A M2 8 0 MP R A M5 0 0 R A M1 0 0 0 R A MT 5 0 0 R A M1 0 0 0 A V...
Page 36: ......
Page 37: ......
Page 48: ......
Page 52: ...15...
Page 71: ...36 Signed MAINTENANCE LOG INTERVENTION 3 Date Technical Assistance Type of Works Signed...
Page 72: ...3 1 Identification of the main parts 2 3 1 4...
Page 73: ...4 5 6 7 8 9 10 11 12 16 13 15 14...
Page 74: ...5 17 15a...
Page 77: ...8 3 Operation 3 1 Control panel...
Page 113: ...34 INTERVENTION 3 Date Technical Assistance Type of intervention Signature...