Chapter 4 : SVG Operation Procedure
4.1 Inspection
Before
Start-up
•
Make sure the module and the cabinet are connected properly and that all screws are
tightened.
•
Make sure each SVG module’s ID and terminal resistance are set properly.
•
The DIP switches used to set the ID and terminal resistance are as shown in
Figure
4-1
.
Table 4-1
lists the locations of DIP switches 1 ~ 4.
(Figure 4-1: Schematic Diagram of DIP Switches)
Item
Item
DIP Switch 1
Setting of the first digit of ID, which is valid when it is slid to right
position.
DIP Switch 2
Setting of the second digit of ID, which is valid when it is slid to right
position.
DIP Switch 3
Setting of the third digit of ID, which is valid when it is slid to right
position.
DIP Switch 4
Setting of terminal resistance, it is activated in right position.
(Figure 4-2: DIP Switch ID0 ~ ID7)
ID=0
Terminal Resistance:
Deactivated
ID=6
Terminal Resistance:
Activated