Wiring Instructions

Installation Manual

48

Communication Connector (CNJ11, CNJ12)

The CNJ11 and CNJ12 connectors are for communication with ESS controller or with other PCS in 
parallel operation. Prepare two RJ45 connectors and six 1.32 mm

2

 wires for each, and connect the 

wires to the pin 1~2 and pin 4~7 of the RJ45 connector as the graphic and pin assignment below:

Figure 48.

CNJ11, CNJ12 Pin Assignment

Table 9: CNJ11, CNJ12 Pin Assignment

Item

Pin Assignment

Notes

CNJ11, CNJ12

1: RS485-A2

For ESS Controller

2: RS485-B2

3: NC

5: CAN-H2

For PCS parallel

6: CAN-L2

7: CAN-H3

For voltage detection

8: CAN-L3

Table 10: Used for Upper Controller (Use 3-pin)

Item

Pin Assignment

Notes

CNJ7

1: RS485A2

The same RS485 terminal as pin1 and pin2 of 
CNJ11/CNJ12, for ESS Controller/Site Controller/
Local Controller/PC.
Used for installation when only one PCS.

2: RS485B2

3: NA

Note:

CNJ11 and CNJ12 are used for parallel operation more than one PCS. When multiple PCSs 
are parallel operated, the network cable should be connected hand by hand, with CNJ11 or 
CNJ12 of the first PCS is connected to upper controller and the terminal resistors should be 
inserted to CNJ11 or CNJ12 of the last one.

PIN 1

PIN 8

PIN 1

PIN 8

P1

P2

CNJ12

CNJ11

Summary of Contents for 100kW PCS

Page 1: ...100kW Power Conditioning System PCS Installation Manual Version 1 0 0...

Page 2: ...ns 3 Typographical Conventions 4 Introduction 5 Overview 5 Features 6 Applications 6 Accessory Kits 6 Installation 7 Before You Begin 7 Unpacking the Unit 12 Installing the PCS Onsite 15 Securing a Ca...

Page 3: ...Installation Manual ii Warranty 60 Appendix 61 Specifications 61 Glossary 63 Screw Torque Table 65...

Page 4: ...r usage to the Manual is prohibited without obtaining Delta s prior written permission As the product will be developed and improved continuously Delta may modify or update the Manual from time to tim...

Page 5: ...About this Manual Installation Manual 1 About this Manual Version Control Table 1 Version Control Rev Change Description Date 1 0 0...

Page 6: ...ard procedure of installing the PCS and information about configuration of the unit It does not provide details of batteries Audience The manual is intended for anyone who needs to install Delta 100kW...

Page 7: ...tion or commissioning of the PCS read through the entire manual and note all DANGER WARNING CAUTION and NOTICE Statements All electrical installations must comply and be in accordance with all the sta...

Page 8: ...rsonnel In operation the PCS wiring and connections can have hazardous high voltages and currents present thus only authorized and qualified personnel shall install and or maintain the PCS In some ope...

Page 9: ...peak shaving enables load shifting for time of use savings and provides real power and reactive power compensation to improve power quality With Delta s PCS solution you can realize the fullest value...

Page 10: ...agement Power Dispatch Load shifting for Time of Use saving Power quality improvement P Q Control Frequency Regulation Emergency backup power Accessory Kits Check that the following items are included...

Page 11: ...nstructions An equipment grounding conductor or a grounded metal and permanent wiring system is required for the PCS connection This should be run with circuit conductors and connected to the equipmen...

Page 12: ...2 05 x 18 11 in as marked in number 1 2 Mounting by the front and rear sides of the unit base Drill four holes for M16 expansion bolts at the 4 corners of an area of 300 x 726 mm 11 81 x 28 58 in as m...

Page 13: ...ired The PCS is forced air cooled The cabinet is separated into two compartments front and rear compartments In the case of front compartment a heat exchanger is mounted on the front door and air is d...

Page 14: ...ise levels The PCS should not be installed in an area that is excessively dusty as this may decrease the performance of the air cooling system The PCS must not be installed in areas in which dust cont...

Page 15: ...ntenance from rear side as shown in Figure 7 Figure 7 Front and Rear Maintenance Clearance Distance When installing the PCS take into consideration the necessary ventilation space as well as the space...

Page 16: ...top cover 3 Remove the top cover Figure 9 Removing a Top Cover WARNING The 100kW PCS and crate have a combined weight of approximately 418 kg 921 lbs DO NOT attempt to lift and or move the package uni...

Page 17: ...Remove the screws securing the left and right sidewalls from the shipping package 5 Remove the right and left sidewalls Figure 10 Removing Left and Right Sidewalls ON OFF STANDB Y RUN FAULT ON AC DIS...

Page 18: ...Remove the front and rear walls Figure 11 Removing Front and Rear Walls Upon unpacking the page inspect the unit for signs of damages that may have been caused during shipping If damage is found immed...

Page 19: ...llation site should be restricted to qualified service personnel Battery Ground Fault Concerns The following are concerns surrounding potential risks of DC ground faults and the possible causes The pr...

Page 20: ...to a lack of knowledge on the part of a rigger To prevent hoisting and rigging hazards it is necessary for the operator to understand the following the weight of the load and rigging hardware the cap...

Page 21: ...om a Pallet CAUTION TO MOVE THE 100KW PCS USE LIFTING EQUIPMENT THAT HAS APPROPRIATELY RATED LIFT CAPACITY CAUTION IF USING LIFTING LUGS BE SURE THE SPREADER BAR IS SUFFICIENTLY LONG TO PREVENT DAMAGE...

Page 22: ...open Figure 13 Opening a Front Panel Make sure the door limiter at the bottom of the panel engages in the track to keep the front panel from closing accidentally Figure 14 Engaging the Front Panel Li...

Page 23: ...anel Figure 15 Opening a Rear Panel Make sure the door limiter at the bottom of the panel engages in the track to keep the rear panel from closing accidentally Figure 16 Locking a Rear Panel in a Cabi...

Page 24: ...rews from the front and rear sides 7 At least two individuals are required to safely lift the top cover Lift both ends simultaneously and remove the top cover from the PCS Place the cover in a clean w...

Page 25: ...nel Make sure the front panel closes correctly with the cabinet The top and bottom of the panel are flush with the cabinet if the panel is closed correctly 11 Rotate the door handle to the locked posi...

Page 26: ...Installation Installation Manual 22 12 Repeat for the rear panel Figure 20 Closing a Rear Panel...

Page 27: ...REQUIRED WEIGHT CAUTION THE UNIT SHOULD NOT BE INSTALLED WITH THE CABINET DOORS OPEN WARNING Before proceeding with the normal operation of the hoist the operator s must be trained accordance with th...

Page 28: ...installation site secure the PCS to the site as described in Securing a Cabinet in a Final Location on page 30 18 Remove the hoist 19 Once the cabinet is secured to the location install the top cover...

Page 29: ...Pallet CAUTION TO MOVE THE 100KW PCS USE A FORKLIFT THAT HAS AN APPROPRIATELY RATED LIFT CAPACITY AND A 915 CM 36 INCH FORK SPAN CAUTION THE ENCLOSURE MUST BE LIFTED FROM THE BOTTOM THE ENCLOSURE MUST...

Page 30: ...rs c Remove the base covers Place them in a clean work surface for later use The covers must be replaced after cabinet installation and cable routing is completed Figure 24 Removing Left and Right Bas...

Page 31: ...aligned insert the forks into the channels until they are completely through the opposite side of the insertion channels f Carefully lift the cabinet Figure 25 Lateral Handling of PCS WARNING Take car...

Page 32: ...sing a PCS from a Pallet b Remove the screws securing the front rear base covers c Remove the front and rear side panels Figure 27 Removing Front Rear Base Covers ON OFF STAND BY RUN FAULT ON AC DIS C...

Page 33: ...pletely through the opposite side of the insertion channels f Carefully lift the cabinet Figure 28 Front rear Side Handling 3 Once the cabinet is secured to the location install the top cover see Secu...

Page 34: ...unlock the front panel b Rotate the door handle to open the front panel and pull the door open Figure 29 Opening a Front Panel Make sure the door limiter at the bottom of the panel engages in the trac...

Page 35: ...nded c Repeat for the rear panel Figure 31 Opening a Rear Panel Make sure the door limiter at the bottom of the panel engages in the track to keep the rear panel from closing accidentally Figure 32 Lo...

Page 36: ...Installation Installation Manual 32 d Install the top cover and secure the top cover to the 100kW PCS with screws Figure 33 Installing the Top Cover...

Page 37: ...ottom of the cabinet are engaged with the front panel g Rotate the door handle to lock Figure 34 Closing a Front Panel Note Make sure there is no gap between the front panel and the cabinet An imprope...

Page 38: ...Installation Installation Manual 34 3 Repeat for the rear panel Figure 35 Closing a Rear Panel...

Page 39: ...nserted in their respective anchoring bolts 6 Repeat for the remaining anchoring bolts 7 Once all nuts are inserted tighten the anchoring bolts in an ascending order See the following figure Figure 36...

Page 40: ...ttery fault 3 Risk to system reliability due to ground fault Shock Hazard Ensure that no DC voltage is being supplied to the PCS and that no AC voltage is present on the AC wiring Failure to do so cou...

Page 41: ...issues such as cracks by stress or holes by penetration in the container create an opportunity for electrolyte to seep out of the container and contact the battery To prevent possible ground fault ri...

Page 42: ...n to OFF state OFF Horizontal turn clockwise to vertical position to ON state Figure 37 PCS Front View with AC DC Disconnects Status ON OFF STANDBY RUN FAULT ON AC DISCONNECT OFF ON DC DISCONNECT OFF...

Page 43: ...o the OFF horizontal position wait at least five minutes before opening the front door 1 Rotate the switch handles to the OFF position to disconnect the AC and DC disconnects Figure 38 Disconnecting t...

Page 44: ...d swing it open until it locks in place Figure 40 Opening a Front Panel Make sure the door limiter at the bottom of the panel engages in the track to keep the front panel from closing accidentally Fig...

Page 45: ...s used the wiring must comply with the local regulations Table 2 AC Wire Sizing and Ratings Cable Type Solid Copper Conductor Voltage Rating 600 Volts or greater Temperature 70 C or greater Gauge 53 4...

Page 46: ...closed in the accessory kit 2 x 6 pin green connector enclosed in the accessory kit 1 x 2 pin green connector enclosed in the accessory kit 1 x 3 pin green connector enclosed in the accessory kit 3 x...

Page 47: ...hes the wire inspection indicator as shown in the following figure Figure 42 Inserting a Power Cable into a Cable Lug Depth Reference Diagram 3 For safety purpose use heat shrinkable tubing on the jun...

Page 48: ...of the unit base and through the wire glands in front of the DC cable glands Plug these connectors into the relevant connector bases built in at the inner side wall of the cabinet adjacent to the DC t...

Page 49: ...m Pin Assignment Notes CNJ3 1 Digital Output 1 1 Dry Contact 1 only for internal use Max 24Vdc 10mA 2 Digital Output 1 2 3 Digital Output 2 1 Dry Contact 2 Max 24Vdc 10mA 4 Digital Output 2 2 5 Digita...

Page 50: ...m the accessory kit For CANbus connect two prepared 1 32 mm2 wires to pins 5 and 6 Figure 46 CNJ13 Pin Assignment Table 7 CNJ13 Pin Assignment Item Pin Assignment Notes CNJ13 1 RS485 B3 For BMS 2 RS48...

Page 51: ...6 wires connected to pins 1 to 6 on the 6 pin connector from the accessory kit as shown in Figure 47 and Table 8 Figure 47 CNJ1 Pin Assignment Table 8 CNJ1 Pin Assignment Item Pin Assignment Notes CNJ...

Page 52: ...er 2 RS485 B2 3 NC 5 CAN H2 For PCS parallel 6 CAN L2 7 CAN H3 For voltage detection 8 CAN L3 Table 10 Used for Upper Controller Use 3 pin Item Pin Assignment Notes CNJ7 1 RS485A2 The same RS485 termi...

Page 53: ...the black start Demand Response Management RJ45 Demand Response Management The inverter provides a RJ45 port to support the connection to a demand response enabling device DRED The support is require...

Page 54: ...the following figure Figure 49 X1 RJ45 Socket Location for DRED Interfacing DRM7 The export power to the grid is no more than 75 of the rated power DRM8 The export power to the grid is 100 of the rate...

Page 55: ...n example As for the other cases please remove the relevant side cover of the unit base to lead the cables and wires into the cabinet To do the wiring works from the front bottom side of the PCS first...

Page 56: ...DC L1 L2 and L3 along with the protective covers and relevant terminals are illustrated See the following figure Figure 52 DC and AC Connection Labels and Terminals Note There are 3 sets of Positive a...

Page 57: ...nd use heat shrinkable tubing on the junction between the cables and lugs to prevent the exposure of the conductive part 2 Remove protective cover of DC terminals Remove the protective cover in front...

Page 58: ...terminals then lead the DC cables with two hole lugs through the DC cable glands into the PCS Connect and secure these cables to the relevant DC and DC terminals Figure 55 Positive and Negative DC Ca...

Page 59: ...ole lugs in the accessory kit and use thermal casing to prevent the exposure of the naked part 2 Remove protective cover of AC terminals Remove the protective cover in front of the AC terminals as the...

Page 60: ...s by Allen wrench then lead the AC cables with two hole lugs through the AC cable glands into the PCS connect and secure these cables to the relevant L1 L2 and L3 terminals Figure 59 AC Cable Connecti...

Page 61: ...copper plate at the inner side wall of the cabinet adjacent to the AC terminals as shown below Figure 61 Grounding Cable Connection with Grounding Copper Bar Note The grounding cable only needs a 53...

Page 62: ...the 1 0 600V wire 2 Remove the nuts securing the plexiglass cover then remove the plexiglass cover Figure 62 Removing the Plexiglass Cover 3 Remove the two hole terminal on the copper bar and crimp t...

Page 63: ...on When PCS100 is configured in IT system application N wire is forbidden to connected to PCS100 Besides the Isolation Monitor Device IMD is essential Customer must install IMD in proper location in t...

Page 64: ...t within the reasonable control of the operation design 4 repaired modified moved or installed by any party without Delta s prior written authorization 5 damage due to accidents such as fire inundatio...

Page 65: ...mpliant Power Factor 1 to 1 continuously adjustable Charging discharging Transfer Time 100 ms 90 rated power Power Response Time 40 ms 0 100 rated power Battery Input Performance DC Voltage Range 750...

Page 66: ...put relays User Interface 4 9 inch LCD screen with push button Fault LEDs Emergency Stop Local EPO button remote control Communication RS 485 Modbus RTU CAN System Characteristic Peak Efficiency 97 2...

Page 67: ...mergency power off ESS Energy storage system Galvanic isolation No conductive connection between two component parts GEC Grounding Electrode Conductor GET Grounding Electrode Terminal IEEE The Institu...

Page 68: ...ded Power dissipation is released mainly as heat PVC Polyvinyl chloride RJ 45 Abbreviation for standardized eight pole electrical connector connection RJ stands for Registered Jack standardized socket...

Page 69: ...red Steel Plate Steel Plate 0 8 0 15 1 4 0 2 2 0 0 2 Steel Plate Aluminum Plate 0 7 0 1 1 0 0 15 1 6 0 2 Aluminum Plate Aluminum Plate Plastic Aluminum Plate 0 6 0 1 0 8 0 15 1 2 0 2 Plastic Steel Pla...