SM150T User Manual 1.0
Operation
11
Installation
Surface installation and spot measurements
Clear away any stones. Pre-form holes in very hard
soils before insertion.
Push the SM150T into the soil until the rods are fully
inserted. Ensure good soil contact.
If you feel strong resistance when inserting the
SM150T, you have probably hit a stone. Stop, and re-
insert at a new location.
Note: The SM150T is not suitable for soil surface
temperature measurements. For soil temperature near the surface dig a
trench and install horizontally as shown below.
Cover both SM150T and the first 30cm of cable with at least 5cm of soil.
Installing at depth
Make a 45mm diameter hole, preferably at about 10°
to the vertical using the
SM-AUG-100
auger.
Connect an extension tube e.g.
ML/EX50
Push the SM150T into the soil until rods are fully
inserted. Ensure good soil contact
.
Alternatively
Dig a trench, and install horizontally.