| O A S I S P O L Y C A R B O N A T E V E R A N D A I N S T A L L A T I O N G U I D E
D
13
10
9
8
9
½B-55mm
½B-55mm
H2
Min. 100mm
Note: If you shorten any of the posts, take into account the depth of the foundation blocks and the
bottom end of the post.
1. Place the post with the PVC rainwater discharge pipe at the location of the rainwater discharge
foundation block.
2. Place the rainwater discharge sleeve in the rainwater discharge foundation block and connect the
rainwater discharge pipe to the sleeve.
Place the post with the rainwater discharge pipe on top of the rainwater discharge foundation block
and fasten the post with M8x40 hex bolts (incl. washers). Make sure the post is level.
3. Place the other posts on the foundation blocks and secure them so they are plumb.
Note: If you shorten any of the posts, take into account the depth of the foundation blocks and the bottom end of the post.
1. Place the post with the PVC rainwater discharge pipe at the location of the rainwater discharge foundation block.
2. Place the rainwater discharge sleeve in the rainwater discharge foundation block and connect the rainwater discharge pipe
to the sleeve. Place the post with the rainwater discharge pipe on top of the rainwater discharge foundation block and fasten
the post with M8x40 hex bolts (incl. washers). Make sure the post is level.
3. Place the other posts on the foundation blocks and secure them so they are plumb.