DD2626171 Rev 0
24 April 2014
201 Daktronics Dr. P.O. Box 5128 Brookings, SD 57006
tel: 866-343-6018 fax: 605-697-4700
www.daktronics.com
DSF-600 Series (Phase 1) Shipping Frame Field Instructions
1 of 1
Lifting
1.
Lift the shipping frame by the lift points. Refer to
Figure 1
.
End view
Side view
45° minimum
Figure 1:
Lifting Shipping Frame
4.
Remove the bolts carefully, ensuring the side panels do not touch the
display section. Refer to
Figure 6
.
Remove bolts at
locations shown
(typical both ends)
Figure 6:
Removing Side Panel
2.
Lift at an angle of 45° or greater. Always lift by the lift points in the
tubes and not by the display section. Refer to
Figure 2
and
Figure 3
.
Figure 2:
Lift Point in Tube
Figure 3:
Lift Point on
Display Section
Disassembling
1.
Remove the shrink wrap carefully.
2.
Unbolt and remove the top support assembly. Refer to
Figure 4
.
Figure 4:
Removing Top
Support Assembly
3.
Unbolt the side panel assemblies from the base assembly at two
locations front and rear. Refer to
Figure 5
.
Figure 5:
Unbolting Side Panel Assemblies
Unbolt and remove these bolts
(both front and rear of frame)
5.
Attach the display section to the crane/lift. Use the special 5.5mm tool
to open the front glass door and to remove the bottom base shrouding.
Refer to
Figure 7
and
Figure 8
. Unbolt the four bolts securing the
display section to the frame base.
Figure 7:
Opening Door
Insert tool in
keyhole and turn
counterclockwise
Figure 8:
Removing Shrouding
Slide cover
up and back
The display section is ready to be installed onto the pre-designed
concrete footing.
Summary of Contents for DAKT-0204-02
Page 10: ...6 Cabinet Installation...
Page 28: ...24 Maintenance Troubleshooting...
Page 32: ......
Page 34: ......
Page 36: ......
Page 41: ......
Page 61: ......