SiK401004_A
115
MAINTENANCE
7. Examination of
System and cooling
medium fillin
●
Pump vacuum and fill cooling medium
if the system leak test passes.
Disassembly and Assembly of capillary
Remark : Make sure that there isn’t any refrigerant in pipe system and the power supply is cut off before removal
of the capillary
Step
Illustration
Handling Instruction
1. Disassembly of
Capillary
●
Weld two welding points connecting
capillary with other pipe lines.
●
Remove capillary.
2. Assembly of New
capillary
●
Install new capillary.
●
Weld the points connected with other
pipe lines.
●
Re-conduct the system leak test.
Pump vacuum and fill the refrigerants.
Disassembly and Assembly of Vapour Liquid Separator
Remark : Make sure that there isn’t any refrigerant in pipe system and the power supply is cut off before removal
of the vapor liquid separator. (the models lowering than 24kBtu/h have no such steps.)
Step
Illustration
Handling Instruction
1. Disassembly of
retaining bolts for liquid
reservoir
●
Disassemble the retaining screws on
the pothooks of the reservoir with
screwdriver.
2. Disassembly of vapor
liquid separator
ffv
●
Weld open two pipes connecting vapor
liquid separator with pipe line with gas
welding.
●
Remove vapor liquid separator.
weld point
capillary
weld point
capillary
Summary of Contents for RY24PEV1K
Page 12: ...SiK401004_A SPECIFICATIONS 4 2 NOMENCLATURE 24 E K M V1...
Page 36: ...SiK401004_A SPECIFICATIONS 28 5 PIPING DIAGRAM...
Page 80: ...SiK401004_A INSTALLATION 72 2 5 Installation Clearance Data Figure 2 5 1...
Page 110: ...SiK401004_A MAINTENANCE 102 3 1 2 R24PEV1K 6 3 6 2 5 6 4 3...
Page 111: ...SiK401004_A 103 MAINTENANCE 3 1 3 RY30PEV1K 6 3 6 2 5 3 6 6...
Page 112: ...SiK401004_A MAINTENANCE 104 3 1 4 R30PEV1K 6 3 6 2 5 6 5 0...
Page 113: ...SiK401004_A 105 MAINTENANCE 3 1 5 RY36PEY1K...
Page 114: ...SiK401004_A MAINTENANCE 106 3 1 6 R36PEY1K L L...
Page 115: ...SiK401004_A 107 MAINTENANCE 3 1 7 RY42PEY1K RY48PEY1K L L...
Page 116: ...SiK401004_A MAINTENANCE 108 3 1 8 R42PEY1K R48PEY1K L L...