5.

Purging air and checking gas leakage

• When piping work is completed, it is necessary to purge the air and check for gas leakage.

 WARNING

• Do not mix any substance other than the specified refrigerant (R410A) into the refrigeration cycle.
• When refrigerant gas leaks occur, ventilate the room as soon and as much as possible.
• R410A, as well as other refrigerants, should always be recovered and never be released directly into the environment.
• Use a vacuum pump for R410A exclusively. Using the same vacuum pump for different refrigerants may damage the vacuum 

pump or the unit.

• If using additional refrigerant, perform air purging from the refrigerant pipes and 

indoor unit using a vacuum pump, then charge additional refrigerant.

• Use a hexagonal wrench (4mm) to operate the stop valve rod.
• All refrigerant pipe joints should be tightened with a torque wrench at the specified 

tightening torque.

*1. Pipe length vs. vacuum pump run time.  

*2. If the compound pressure gauge pointer swings back, refrigerant may have water content or a loose pipe joint may exists.  

Check all pipe joints and retighten nuts as needed, then repeat steps 2) through 4).

1) Connect projection side of charging hose (which comes from gauge manifold) to gas stop valve’s service port.

2) Fully open gauge manifold’s low-pressure valve (Lo) and completely close its high-pressure valve (Hi).  

(High-pressure valve subsequently requires no operation.)

3)  Do vacuum pumping and make sure that the compound pressure gauge reads –0.1MPa (–76cmHg).*1

4) Close gauge manifold’s low-pressure valve (Lo) and stop vacuum pump.  

(Keep this state for a few minutes to make sure that the compound pressure gauge pointer does not swing back.)*2

5) Remove caps from liquid stop valve and gas stop valve.

6) Turn the liquid stop valve’s rod 90 degrees counterclockwise with a hexagonal wrench to open valve. 

Close it after 5 seconds, and check for gas leakage.
Using soapy water, check for gas leakage from indoor unit’s flare and outdoor unit’s flare and valve rods.  
After the check is complete, wipe all soapy water off.

7) Disconnect charging hose from gas stop valve’s service port, then fully open liquid and gas stop valves.

(Do not attempt to turn valve rod beyond its stop.)

8) Tighten valve caps and service port caps for the liquid and gas stop valves with a torque wrench at the specified torques.

Pipe length

Up to 15m

More than 15m

Run time

Not less than 10 min.

Not less than 15 min.

Compound 
pressure gauge

Pressure 
metre

High-
pressure 
valve

Low-pressure 
valve

Vacuum pump

Service port

Liquid 
stop 
valve

Valve caps

Gas stop valve

Charging 
hoses

Gauge 
manifold

01_EN_3P254362-3E.fm  Page 6  Tuesday, December 7, 2010  7:32 PM

Summary of Contents for RXG25K2V1B

Page 1: ...t series Montaj k lavuzlar R410A Split serisi Installationsanleitung Split Baureihe R410A Manuel d installation S rie split R410A Montagehandleiding R410A Split systeem Manual de instalaci n Serie Spl...

Page 2: ...DUSTRIES LTD Low Voltage 2006 95 EC Electromagnetic Compatibility 2004 108 EC 3SB64564 15G RXG25K2V1B RXG35K2V1B Shinri Sada Manager Quality Control Department DAIKIN TCF 015 N9 01 2011 KEMA Quality B...

Page 3: ...Center Bldg 2 4 12 Nakazaki Nishi Kita ku Osaka 530 8323 Japan RXG25K2V1B RXG35K2V1B 3SB64417 13L Shinri Sada Manager Quality Control Department 3SB64417 13L fm Page 1 Wednesday February 16 2011 10 3...

Page 4: ...3SB64417 13L fm Page 2 Wednesday February 16 2011 10 38 AM...

Page 5: ...ls If refrigerant gas leaks during installation ventilate the area immediately Toxic gas may be produced if the refrigerant comes into contact with fire After completing installation check for refrige...

Page 6: ...8 In coastal areas or other places with salty atmosphere of sulfate gas corrosion may shorten the life of the air conditioner 9 Since drain flows out of the outdoor unit do not place under the unit a...

Page 7: ...necting the FVXG indoor unit the shortest piping length should be no less than around 2 5m 1 5m Min allowable length CAUTION Set the piping length from 1 5m to 20m Wrap the insulation pipe with the fi...

Page 8: ...door Unit Installation 1 Installing outdoor unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawings 2 If drain work is necess...

Page 9: ...hes when tightening the flare nuts to prevent damage to the flare nuts and gas leakage Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand Then tighten them fully with the...

Page 10: ...p valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve subsequently requires no operation 3 Do vacuum pumping an...

Page 11: ...on dimensions as below 3 Use separate thermal insulation pipes for gas and liquid refrigerant pipes Gas side Liquid side Gas pipe thermal insulation Liquid pipe thermal insulation O D 9 5mm O D 6 4mm...

Page 12: ...ff if has not been turned off 2 Remove the stop valve cover 3 Disconnect the selective connector for standby electricity saving 4 Turn on the main power supply CAUTION Before connecting or disconnecti...

Page 13: ...the same time 4 Press MODE button twice will be displayed and the unit will enter trial operation Trial operation will stop automatically after around 30 minutes To stop trial operation press ON OFF...

Page 14: ...supply terminal board Precautions to be taken for power supply wiring Use a round crimp style terminal for connection to the power supply terminal board In case it cannot be used due to unavoidable r...

Page 15: ...unt of power in its standby mode If the system is not to be used for some time after installation shut off the circuit breaker to eliminate unnecessary power consumption If the circuit breaker trips t...

Page 16: ...1102 HT 3P254362 3E M10B207 Two dimensional bar code is a code for manufacturing 00_CV_3P254362 3E fm Page 2 Tuesday December 7 2010 7 19 PM...

Reviews: