Pre-run checks

Be sure to perform a test run.

Be sure to fully open the liquid-side and gas-side stop valves. If
you operate the unit with stop valves closed, the compressor will
break down.

Be sure to execute the first test run of the installation in cooling
mode operation.

Never leave the unit unattended with an open front panel during
test run.

To  protect the compressor, make sure to turn on the power
supply 6 hours before starting operation.

During tests never pressurize the applications with a pressure
higher than the maximum allowable pressure (indicated on the
name plate of the unit).

Test run

Carry out the test run in accordance with the indoor installation
manual to ensure that all functions and parts are working properly.

Failure diagnosis at the moment of first installation

In case nothing is displayed on the remote controller (the current
set temperature does not display), check for any of the following
abnormalities before you can diagnose possible malfunction
codes.

Disconnection or wiring error (between power supply and
outdoor unit, between outdoor unit and indoor units, between
indoor unit and remote controller).

The fuse on the outdoor unit PCB may have run out.

If the remote controller shows "

E3

", "

E4

or "

L8

" as an error code,

there is a possibility that either the stop valves are closed, or that
air inlet or air outlet are blocked.

If the error code "

U2

" is displayed on the remote controller, check

for voltage imbalance.

If the error code 

"L4"

 is displayed on the remote controller, it is

possible that air inlet or air outlet are blocked.

The reversed phase protection detector of this product only
works during the initialisation stage after a power reset.
The reversed phase protection detector is designed to stop the
product in case of an abnormality when the product is started
up.

When the reversed phase protection circuit forced the unit to
stop, check if all phases are existing. If this is the case, shut
off the power supply to the unit and replace two of three
phases. Turn on power again and start the unit.

Reversed phase detection is not performed while the product
is operating.

In case of possible reversal of phases after a momentary
black out of power and the power goes on and off while the
product is operating, install a reversed phase protection
circuit on site. Such situation is not unimaginable when using
generators. Running the product in reversed phase can
break the compressor and other parts.

For a missing phase in case of W1 units, "

E7

"  or  "

U2

"  will be

displayed on the remote controller of the indoor unit.
Operation will be impossible with either one of these
phenomena. If this happens, turn off the power, re-check the
wiring and switch the position of two of the three electrical wires.

DANGER

Never leave the unit unattended during installation or
servicing. When the service panel is removed live parts
can be easily touched by accident..

NOTE

Note that during the first running period of the unit,
required power input may be higher than stated on the
nameplate of the unit. This phenomenon originates
from the compressor that needs elapse of a 50 hours
run in period before reaching smooth operation and
stable power consumption.

Items to check

Electrical wiring
Inter-unit wiring
Earth wire

Is the wiring as mentioned on the wiring diagram?
Make sure no wiring has been forgotten and that
there are no missing phases or reverse phases.

Is the unit properly earthed?

Is the wiring between units connected in series
correct?

Are any of the wiring attachment screws loose?

Is the insulation resistance at least 1 M

?

-

Use a 500 V mega-tester when measuring 
insulation.

-

Do not use a mega-tester for low-voltage circuits.

Refrigerant 
piping

Is the size of the piping appropriate?

Is the insulation material for the piping attached
securely?
Are both the liquid and gas pipes insulated?

Are the stop valves for both the liquid side and the
gas side open?

Extra 
refrigerant

Did you write down the extra refrigerant and the
refrigerant piping length?

Summary of Contents for ERLQ011BAV3

Page 1: ...STALLATION MANUAL ERHQ011BAV3 ERHQ014BAV3 ERHQ016BAV3 ERHQ011BAW1 ERHQ014BAW1 ERHQ016BAW1 ERLQ011BAV3 ERLQ014BAV3 ERLQ016BAV3 ERLQ011BAW1 ERLQ014BAW1 ERLQ016BAW1 Outdoor unit for air to water heat pum...

Page 2: ...1 2 4 5 6 3 1 3 2 4 5 A B A E B C D H H L A A B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 A A B1 B1 B1 B1 B1 B1 B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 1 1 2...

Page 3: ...prescrizioni per 07 v v v 08 de acordo com o previsto em 09 10 under iagttagelse af bestemmelserne i 11 enligt villkoren i 12 gitt i henhold til bestemmelsene i 13 noudattaen m r yksi 14 za dodr en u...

Page 4: ...t does not exceed the concentration limit in the event of a leakage Otherwise this may lead to an accident due to oxygen depletion Be sure to use only the specified accessories and parts for installat...

Page 5: ...ns on page 3 Improper drain piping may cause water leakage and make the furnitures get wet Install the indoor and outdoor units power wire and connecting wire at least 1 meter away from televisions or...

Page 6: ...rinding works where a lot of dust is created the unit must be covered Do not place any objects or equipment on top of the unit top plate Do not climb sit or stand on top of the unit Be sure that suffi...

Page 7: ...l not affect the unit If lateral snowfall is possible make sure that the heat exchanger coil is not affected by the snow if necessary construct a lateral canopy PRECAUTIONS ON INSTALLATION Check the s...

Page 8: ...REFRIGERANT PIPE SIZE AND ALLOWABLE PIPE LENGTH A Location of the 2 fixation holes on the front side of the unit B Location of the 2 fixation holes on the rear side of the unit C Wires field supply S...

Page 9: ...ded when passing copper tubes through walls Piping should be mounted so that the flare is not subjected to mechanical stress Flaring guidelines Flares should not be re used New ones should be made in...

Page 10: ...t the operating pressure will be low for example when cooling will be performed while the outside air temperature is low sufficiently seal the flare nut in the stop valve on the gas line with silicon...

Page 11: ...tion Be careful not to let the indoor and outdoor piping come into contact with the compressor terminal cover If the liquid side piping insulation might come into contact with it adjust the height as...

Page 12: ...inimum gauge pressure of 0 2 MPa 2 bar Never set the gauge pressure higher than the maximum operation pressure of the unit i e 4 0 MPa 40 bar 2 2 Test for leaks by applying a bubble test solution to a...

Page 13: ...syphon attached or not and position the cylinder accordingly NOTE National implementation of EU regulation on certain fluorinated greenhouse gases may require to provide the appropriate official nati...

Page 14: ...ally 5 Once operation stops after 3 to 5 minutes close the liquid stop valve and the gas stop valve 6 The pump down operation is now finished The remote controller may display U4 and the indoor pump m...

Page 15: ...re the wiring in the order shown below 1 Secure the earth wire to the stop valve attachment plate so that it does not slide 2 Secure the earth wire to the stop valve attachment plate one more time alo...

Page 16: ...r unit for wiring of indoor unit etc Attach an earth leakage circuit breaker and fuse to the power supply line See figure 6 In wiring make certain that prescribed wires are used carry out complete con...

Page 17: ...ase protection circuit forced the unit to stop check if all phases are existing If this is the case shut off the power supply to the unit and replace two of three phases Turn on power again and start...

Page 18: ...ntling of the unit treatment of the refrigerant of oil and of other parts must be done in accordance with relevant local and national legislation UNIT SPECIFICATIONS Technical specifications Electrica...

Page 19: ...y S1NPH Pressure sensor S1PH Pressure switch high TC Signal transmission circuit for V3 models only V1R Power module for V3 models only V1R V2R Power module for W1 models only V2R V3R Diode module for...

Page 20: ...4PW54249 1 Copyright Daikin...

Reviews: