background image

ERHQ011~W1 + ERLQ011~W1

Outdoor unit for air to water heat pump

4PW54249-1

Installation manual

12

E

LECTRICAL

 

WIRING

 

WORK

Precautions on electrical wiring work

Use only copper wires.

A main switch or other means for disconnection, having a
contact separation in all poles, must be incorporated in the fixed
wiring in accordance with relevant local and national legislation.
Do not turn on the main switch until all the wiring is completed. 

For W1
Make sure to connect power supply cables in normal phase. If
connected in reverse phase, the remote controller of the indoor
unit indicates "

U1

"  and the equipment cannot operate. Change

any two of the three power supply cables (L1, L2, L3) to correct
phase.

Never squeeze bundled cables into a unit.

Fix cables so that cables do not make contact with the pipes
(especially on high pressure side).

Secure the electrical wiring with cable ties as shown in the figure
below so that it does not come in contact with the piping,
particularly on the high-pressure side.
Make sure no external pressure is applied to the terminal
connectors.

When installing the earth leakage circuit breaker make sure that
it is compatible with the inverter (resistant to high frequency
electrical noise) to avoid unnecessary opening of the earth
leakage circuit breaker.

As this unit is equipped with an inverter, installing a phase
advancing capacitor not only will deteriorate power factor
improvement effect, but also may cause capacitor abnormal
heating accident due to high-frequency waves. Therefore, never
install a phase advancing capacitor.

Secure the wiring in the order shown below.

1

Secure the earth wire to the stop valve attachment plate so that
it does not slide.

2

Secure the earth wire to the stop valve attachment plate one
more time along with the electric wiring and the inter-unit wiring.

Lay the electrical wiring so that the front cover does not rise up
when doing wiring work and attach the front cover securely.

All wiring must be performed by an authorized
electrician.

All components procured on the site and all electric
construction shall comply with the applicable local and
national regulations.

DANGER

High voltage

To  avoid electrical shock, make sure to disconnect the
power supply 1 minute or more before servicing the
electrical parts. Even after 1 minute, always measure the
voltage at the terminals of main circuit capacitors or
electrical parts and, before touching, make sure that those
voltages are 50 V DC or less.

To persons in charge of electrical wiring work:

Do not operate the unit until the refrigerant piping is
complete. (Running it before the piping is ready will break
the compressor.)

DANGER

Before obtaining access to terminal devices, all supply
circuits must be interrupted.

DANGER

Be sure to install an earth leakage circuit breaker in
accordance with relevant local and national
regulations. Failure to do so may cause electrical
shock.

CAUTION

Be sure to install the required fuses.

1

Switch box

2

Stop valve mounting plate

3

Earth

4

Cable tie

5

Wiring between units

6

Power supply and earth wiring

Only if bottom plate heater applicable (ERLQ or optional)

7

Bottom plate heater cable

8

Power supply of bottom plate heater (from indoor unit)

1

Power supply, earth wiring, and if applicable: bottom plate heater 
wire

2

Wiring between unit

4

3

3

3

2

1

V3

W1

5

8

6

4

7

5

8

6

7

1

2

1

2

1

2

Summary of Contents for ERLQ011BAV3

Page 1: ...STALLATION MANUAL ERHQ011BAV3 ERHQ014BAV3 ERHQ016BAV3 ERHQ011BAW1 ERHQ014BAW1 ERHQ016BAW1 ERLQ011BAV3 ERLQ014BAV3 ERLQ016BAV3 ERLQ011BAW1 ERLQ014BAW1 ERLQ016BAW1 Outdoor unit for air to water heat pum...

Page 2: ...1 2 4 5 6 3 1 3 2 4 5 A B A E B C D H H L A A B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 A A B1 B1 B1 B1 B1 B1 B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 1 1 2...

Page 3: ...prescrizioni per 07 v v v 08 de acordo com o previsto em 09 10 under iagttagelse af bestemmelserne i 11 enligt villkoren i 12 gitt i henhold til bestemmelsene i 13 noudattaen m r yksi 14 za dodr en u...

Page 4: ...t does not exceed the concentration limit in the event of a leakage Otherwise this may lead to an accident due to oxygen depletion Be sure to use only the specified accessories and parts for installat...

Page 5: ...ns on page 3 Improper drain piping may cause water leakage and make the furnitures get wet Install the indoor and outdoor units power wire and connecting wire at least 1 meter away from televisions or...

Page 6: ...rinding works where a lot of dust is created the unit must be covered Do not place any objects or equipment on top of the unit top plate Do not climb sit or stand on top of the unit Be sure that suffi...

Page 7: ...l not affect the unit If lateral snowfall is possible make sure that the heat exchanger coil is not affected by the snow if necessary construct a lateral canopy PRECAUTIONS ON INSTALLATION Check the s...

Page 8: ...REFRIGERANT PIPE SIZE AND ALLOWABLE PIPE LENGTH A Location of the 2 fixation holes on the front side of the unit B Location of the 2 fixation holes on the rear side of the unit C Wires field supply S...

Page 9: ...ded when passing copper tubes through walls Piping should be mounted so that the flare is not subjected to mechanical stress Flaring guidelines Flares should not be re used New ones should be made in...

Page 10: ...t the operating pressure will be low for example when cooling will be performed while the outside air temperature is low sufficiently seal the flare nut in the stop valve on the gas line with silicon...

Page 11: ...tion Be careful not to let the indoor and outdoor piping come into contact with the compressor terminal cover If the liquid side piping insulation might come into contact with it adjust the height as...

Page 12: ...inimum gauge pressure of 0 2 MPa 2 bar Never set the gauge pressure higher than the maximum operation pressure of the unit i e 4 0 MPa 40 bar 2 2 Test for leaks by applying a bubble test solution to a...

Page 13: ...syphon attached or not and position the cylinder accordingly NOTE National implementation of EU regulation on certain fluorinated greenhouse gases may require to provide the appropriate official nati...

Page 14: ...ally 5 Once operation stops after 3 to 5 minutes close the liquid stop valve and the gas stop valve 6 The pump down operation is now finished The remote controller may display U4 and the indoor pump m...

Page 15: ...re the wiring in the order shown below 1 Secure the earth wire to the stop valve attachment plate so that it does not slide 2 Secure the earth wire to the stop valve attachment plate one more time alo...

Page 16: ...r unit for wiring of indoor unit etc Attach an earth leakage circuit breaker and fuse to the power supply line See figure 6 In wiring make certain that prescribed wires are used carry out complete con...

Page 17: ...ase protection circuit forced the unit to stop check if all phases are existing If this is the case shut off the power supply to the unit and replace two of three phases Turn on power again and start...

Page 18: ...ntling of the unit treatment of the refrigerant of oil and of other parts must be done in accordance with relevant local and national legislation UNIT SPECIFICATIONS Technical specifications Electrica...

Page 19: ...y S1NPH Pressure sensor S1PH Pressure switch high TC Signal transmission circuit for V3 models only V1R Power module for V3 models only V1R V2R Power module for W1 models only V2R V3R Diode module for...

Page 20: ...4PW54249 1 Copyright Daikin...