NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
11.3 Checklist before commissioning
After the installation of the unit, first check the items listed below. Once all checks
are fulfilled, the unit MUST be closed. Power-up the unit after it is closed.
You read the complete installation instructions, as described in the
installer reference
guide
.
The
indoor unit
is properly mounted.
The
outdoor unit
is properly mounted.
The following
field wiring
has been carried out according to this document and the
applicable legislation:
▪
Between the local supply panel and the outdoor unit
▪
Between indoor unit and outdoor unit
▪
Between the local supply panel and the indoor unit
▪
Between the indoor unit and the valves (if applicable)
▪
Between the indoor unit and the room thermostat (if applicable)
The system is properly
earthed
and the earth terminals are tightened.
The
fuses
or locally installed protection devices are installed according to this document,
and have NOT been bypassed.
The
power supply voltage
matches the voltage on the identification label of the unit.
There are NO
loose connections
or damaged electrical components in the switch box.
There are NO
damaged components
or
squeezed pipes
on the inside of the indoor and
outdoor units.
Backup heater circuit breaker
F1B (field supply) is turned ON.
The correct pipe size is installed and the
pipes
are properly insulated.
There is NO
water leak
inside the indoor unit.
The
shut-off valves
are properly installed and fully open.
The
automatic air purge
valves are open.
The
pressure relief valve
purges water when opened. Clean water MUST come out.
The
domestic hot water tank
is filled completely.
11.4 Checklist during commissioning
The
minimum flow rate
during backup heater/defrost operation is guaranteed in all
conditions. See "To check the water volume and flow rate" in
71].
To perform an
air purge
.
To perform a
test run
.
Summary of Contents for Altherma EAVH16S23DA6V
Page 228: ...11 11...
Page 229: ......
Page 230: ......
Page 231: ......
Page 232: ...4P556070 1A 2021 09 Copyright 2018 Daikin Verantwortung f r Energie und Umwelt...