12
ELECTRICAL WIRING
WARNING !!!
:
Danger of electrical shock is poss ible while connecting the wiring on this equi pment
.
Take special care when connecting any electrical wires. Ensure that ALL power is switched off or isolated before any
connections are m ade. This equipment is supplied with a 16 volt AC transform er. Do not open or tam per with the
transform er as this could cause electrical shock.
The transformer delivers a 16 volt AC out-put to the charger on the m ain P.C.Board. This 16 volt supply will keep the
battery charged. The battery operates the m otor. In the case of mains power failure, the battery will continue to operate the
m otor as normal until the battery goes flat. The m otor will then stop operating.
Note
: this is a battery operated m otor and will not operate with a flat battery regardless of the m ains supply being
switched on.
The 16 volt AC wiring from the transform er in the house to the charger on the m ain P.C.Board m ust be run in a conduit
from the house to the m otor. The conduit m ust term inate inside the m otor. No j oins in the cable should be made between
the transformer and the m otor.
The cable used to run the 16 volt AC from the transformer to the charger should be a m inim um of a three core 1.5mm
cable. The conduit should have no sharp bends in it as this may cause problem s in the future if the cable needs to be
pulled out and replaced. The conduit should be buried 300mm underground.
DO NOT RUN 220 VOLTS IN THE SAME CONDUIT AS 16 VOLTS.
Connect the E (earth) from the transform er to the
green and yellow wire
on the main P.C.Board.
16 VOLTS AC
16 VOLTS AC
EARTH
Transformer
Main P.C.Board
COMPACT 300
WIRING
17
SETTING THE MOTOR DIRECTION
FOR A GATE CLOSING TO THE LEFT
FOR A GATE CLOSING TO THE RIGHT
BLUE WIRE
BLACK WIRE
BLUE WIRE
BLACK WIRE
Closing direction
Closing direction
The following diagram s show the correct wiring of the electric m otor to the main P.C.Board. The m otor wires are found
protruding from the m otor, there are two wires, one wire is blue in colour the other wire is black in colour.
PROG RAMMING THE MOTOR
The m otor m ust be programm ed to the gate in order to operate correctly . .
It is im portant to note that the following points should be checked before the gate is programm ed.
1.
Motor is level.
2.
Rack is secure to the gate and engaged with the pinion gear.
3.
The gate has adequate end stops. (
DO NOT
automate a gate without end stops.)
4.
The gate runs freely and does not jam at
ANY
part of travel.
5.
The magnet is m ounted correctly . (Com pact 500 only)
TO PROGRAM THE MOTOR. Ensure that all power is rem oved from the board.
1.
Manually open the gate 1m -1.5m This will be the pedestrian opening distance.
2.
Lock the gate in place. (Operational m ode.)
3.
Insert the program j um per over the two pins on the P.C. Board called “prog m otor”.
4.
Apply the battery power. The status L.E.D. will flash rapidly .
5.
Press the trigger button. on the P.C.Board. The gate will automatically do the following
6. A)
Close
slowly until the end stop is struck.
B)
Open
slowly until the end stop is struck.
7. When the m otor is fully open. Rem ove the j um per from the prog m otor pins.
8. Apply the AC m ains power and ensure that the green “charge” led comes on.
The m otor is now fully programm ed and ready for norm al use.
NOTE
the programm ing procedure can be aborted at any stage sim ply by rem oving the battery wires. This will stop the m otor
and the process can be re-started at any tim e.
In
step (6 A)
the gate m ust close first. If the gate opens first, then the
motor wires
m ust be reversed. This will change the
m otor direction. {See Setting the m otor direction}
Do not
connect any other trigger wires to the board until the m otor is fully programmed.
PTO for programming diagram.