8. First start - Commissioning
8.1 Before first start
Check that:
1. the boiler and heating system are filled with water.
2. all connections are tight and that the chimney connection is made in an correct way.
3. the oil tank is inspected according to existing regulations.
4. an oil filter is fitted to the burner.
5. the electrical connections are made in an correct way.
6. all sensors, burner, mixing valve and pumps are connected to the power supply.
8.2 First start
1. Switch on the current with the mains switch.
2. By commissioning applies the Comfort-control the factory pre-set standard values
for set points, time program and operating modes. Though is it prerequisite to make
settings of the time of the day and date. Further adjustments for personal
requirements are performed according to the technical manual of the Comfort-
control.
See also the part Electrical installation – Comfort-control.
3. Check that the oil burner starts.
4. When the boiler has reached its operating temperature, check and adjusts
the oil burner in accordance with its technical manual.
See also the part Oil burner.
8.3 After first start
Check that:
1. all pipe connections are tight, tighten if necessary.
2. the flue duct is tight and well insulated.
3. the boiler temperature rises upon first start.
4. heat goes out to the heating system
5. the heating circuit pump is running and can be controlled from the Comfort-control
of the boiler.
6. the tapping points of the house are provided with hot water as the boiler has turned
warm.
7. the function of the safety valve is faultless.
8. the boiler and the heating system are well vented. Re-check after a few days.
Summary of Contents for CTC 380 IC
Page 2: ......
Page 3: ...CTC 380 IC Models 17 19 24 29 162 105 11 1 2013 05 21...
Page 4: ......
Page 6: ...CTC 380 IC 6...
Page 45: ...CTC 380 IC 45...
Page 46: ......
Page 67: ...21 Boiler 8 ELECTRICAL EQUIPMENT 380IC 17 19 8 1 Wiring diagram LMO14 113...
Page 73: ......
Page 74: ......
Page 75: ......