APP Interface
35 / 79
IMPORTANT!
Please check with your local electricity supply company before
selecting a Grid Code. If the inverter is operated with a wrong
Grid Code, the electricity supply company may cancel the
interconnection agreement.
Placing the inverter into operation before the overall system
complies with the national rules and safety regulations of the
application is not permitted.
5.
When the device screen shows the normal operation status and the RUN
light on the LED panel is illuminated, it indicates that the grid connection
and power generation are successful. You can now browse through the
real-time data in the APP now.
6.
If the inverter fails to operate normally, the FAULT light will illuminate and
the fault information will be shown on the interface. You can touch the
History
icon to check the detailed fault information. Troubleshoot related
problems and restart. Contact our after-sale department if necessary.