CPI SATCOM & Antenna Technologies
1.8M SERIES 1184
12
STEP 6:
STEP 7:
STEP 8:
A). Rotate azimuth rod or the positioner so
that the hole in the azimuth rod and the
hole in the tab on the side of the
positioner are lined up.
B). Secure the azimuth rod to the positioner
with the
1 / 2” hardware removed in step1.
C). Lightly tighten all of the azimuth
adjustment hardware at this time.
1 / 2” Hardware
Positioner
Azimuth Rod
A). Remove 1” hardware form the reflector
support tube.
B). Remove 1 / 2” hardware from the elevation
adjustment block and set aside.
1” Hardware
Reflector
Support Tube
1 / 2” Hardware
Elevation Adjustment Block
A). Place the reflector support tube in
between the large tabs on the positioner
as shown.
B). Line up the holes on the tabs with the
holes in the reflector support tube.
C). Secure the support tube to the positioner
with the 1” hardware.
1” Hardware
Large Tabs
Reflector Support
Tube