Final steps
6720816962-37.1ST
1.
Fig. 60 Inserting the intermediate reflector
>
Carefully press in the intermediate reflector from top to
bottom. (1.-6.)
>
Use a clip to secure the intermediate reflector at the top
and bottom. (7.)
click
7.
6720816962-47.1ST
1.
2.
3.
4.
5.
6.
7.
click
Fig. 61 Installing the intermediate reflector between the collectors
10.4 Installing the end cap and intermediate panel
Only install the intermediate panel and end cap
after
the
hydrostatic test has been performed.
>
Insert the intermediate panel from below into the collec-
tor profile. [1.]
>
Press the intermediate panel forward until it audibly
locks into place. [2.]
>
Fix the end cap with a Torx T10. [3.]
6720816962-38.1ST
T15
1.
2.
click
3.
Fig. 62 Install the end caps (in this case, same-side connection)
10.5 Insulating the connection lines and pipework
>
Thermally insulate the pipework in the entire solar
circuit in accordance with regulations.
>
Thermally insulate the external pipework using material
which is resistant to UV rays, weather influences and
high temperatures (150 °C).
>
Insulate internal pipework with high temperature-resis-
tant (150 °C) material.
>
Protect the insulation against damage from birds if
required.
10.6 Removing the collector film
In order for the film to be removed residue-free, do not
leave the film on the collector for more than four weeks after
installation.
If the system cannot be commissioned after four
weeks:
>
Cover the collectors at the installation site.
>
Remove the film after commissioning the solar system.
6720816963.30-1.ST
Fig. 63 Removing the collector film