7 Start-up
7.1 General description
The indicated operations should be done by qualified technician with specific training on the product.
Upon request, the service centres performing the start-up.
The electrical, water connections and the other system works are by the installer.
Agree upon in advance the star-up data with the service centre.
Before checking, please verify the following:
•
the unit should be installed properly and in conformity with this manual
•
the electrical power supply line should be isolated at the beginning
•
the unit isolator is open, locked and equipped with the suitable warning
•
make sure no tension is present
After turning off the power, wait at least 5 minutes before accessing to the electrical panel or any other electrical component.
Before accessing check with a multimeter that there are no residual stresses.
7.2 Preliminary checks
For details refer to the different manual sections.
Unit OFF power supply
1. safety access
2. functional spaces
3. air flow: correct return and supply (no bypass, no stratification)
4. structure integrity
5. fans run freely
6. unit on vibration isolators
7. air filters present and clean
8. completed aeraulic system
9. refrigerant circuit visual check
10. earthing connection
11. power supply features
12. electrical connections provided by the customer
7.3 Start-up sequence
For details refer to the different manual sections.
Unit ON power supply
1. the compressor crankcase heating elements have been running for at least 12 hours
2. off-load voltage measure
3. phase sequence check
4. shut-off valve refrigerant circuit open
5. unit ON
6. load voltage measure and absorptions
7. check all fan operating
8. check air flow on outer coil (no by-pass, no stratification)
9. air flow rate measurement
10. supply, return and outdoor air temperature measurement
11. measure super-heating and sub-cooling
12. check no anomalous vibrations are present
13. climatic curve personalization
14. climatic curve personalization
15. scheduling personalization
16. fire alarm configuration *
17. complete and available unit documentation
* only if present
Summary of Contents for CKN-XHE2i 10.1
Page 7: ...M06K40A18 00 CKN XHE2i 7 1 14 2 7...
Page 16: ...16 CKN XHE2i 7 1 14 2 M06K40A18 00 6 5 Connections performer by customer...
Page 44: ...M06K40A18 00 CKN XHE2i 7 1 14 2 44 Fans...
Page 45: ...4 CKN XHE2i 7 1 14 2 M06K40A18 00 VALVES Only value 14 2...
Page 51: ...5 CKN XHE2i 7 1 14 2 M06K40A18 00 Flue stack assembly...
Page 53: ...5 CKN XHE2i 7 1 14 2 M06K40A18 00 10 6 Hot water coil...
Page 65: ......