4.
Installation instructions
1
.
C-Post installation
1a. Before starting, check you have
the installation tools needed.
Position the required components
close to the installation location.
Make sure that the hydraulic pile
driver equipment is suitable for your
particular installation.
Mark the line of the post array.
1b. Obtain the maximum allowed
distance between posts and the
minimum embedment length from
the relevant engineering certificate
and/or project drawing. If you don’t
have this document, please contact
the Clenergy customer service.
Mark the positions of the posts (you
can use a string and a tape
measure or a GPS) and drive the
posts into the ground. Make sure all
posts are in line and set to the
correct height according to the
drawing (you can use a sting or a
laser tool).
Note: apply zinc coating to upper
section (circled) of C-Post after
piling. The reason for that is that
ramming can damage the
galvanisation of the posts.
2
.
Post head installation
Install the post head and fix it with
the two M12 bolts and nuts
supplied. To avoid stainless steel
galling/seizing apply grease or
lubricant if needed.
Recommended torques:
Bolt 1: 55 Nm
Bolt 2: 23 Nm
Apply Zinc Coating to upper section
of C Post after ramming
Bolt 1
Bolt 2