Installation Instruction
Fix the Angle Bracket to the Isolator Shade
and then fix the assembled Isolator Shade
on the Rail as shown in the Figure on the
right.
Note: Allow space above the Rail for the
Isolator Shade Cover to open fully.
Recommended torque for M8 Bolts for
fixing Angle Bracket on Isolator Shade is
8-10N·m.
Recommended torque for M8 Bolt for
fixing Isolator Shade on the Rail is 16-
20N·m.
After cable installation, close the Isolator
Cover as shown in the Figure on the right.
5.5.2 Cable Clip Installation
- Click the top end of the Cable Clip into
the channel on the back of the rail.
- Push the other end of the clip in to the
rail channel, using a rubber mallet if
required.