RAFTER AND MAIN FRAME ASSEMBLY (continued)
6. Locate the first two rafter pipes for the second rafter and
slide each into a mounted rafter foot.
ATTENTION:
Order of pipes is opposite that of the end
rafter.
Verify that the purlin holes of the second rafter pipes
are toward the end rafter. Holes will align with the those of
the end rafter. See diagrams to the right.
7. Using the diagrams below and the previous steps, assemble
the remainder of the second rafter, including the purlins as
shown below. Remember to install a Tek screw in the center
hole of each coupler to set the rafter depth. Verify that you
have selected the correct rafter and purlin pipes and have
placed them in the correct location.
8. After assembling the rafter and adding the purlins, return
to both rafters and install FA4482B Tek screws through all
remaining coupler holes and into the rafter pipes.
IMPORTANT:
Also install a Tek screw through each purlin
pipe and into the coupler pipe.
To prevent cover wear,
use the supplied tape to tape over the heads of the Tek
screws on the outer edge of each end rafter coupler.
125P058
100P0625
A
D
C
B
36HB287P4E
36HB287P2E
36HB287P1E
36HB287P3E
C
100P0625
Second
Rafter
D
100P0625
End
Rafter
B
125P058
CP287X125M
FA4482B
A
CP287X125E
125P058
FA4482B
End
Rafter