CLEARSPAN
™
POLY BUILDINGS
36
Revision date: 05.20.20
20
The following procedure describes installing an
end panel that includes D-rings at the top and a
horizontal pocket sealed at or near the bottom of
the panel. Complete these steps to install an end
panel of this design.
Required parts include:
• End panel(s) and 103620E 1" strap
• QH1061 ratchets and AJ104B lag bolts
• 131S075 pipe and FA4482B Tek screws
Outside view of the
sample end panel.
1. Position the panel flat on ground with the long edge placed along the wood end frame of the building.
(The D-rings will be visible when the panel is positioned properly.)
2. Locate the D-rings near the top edge of the panel and tie a section of 1" strapping (or rope) to the
center-most D-ring. Tie two additional straps on each side of the center D-ring, allowing a few feet to
remain between the straps.
3. With the temporary straps (or customer-supplied rope) in place, pull the end panel up to the end rafter
and secure the end panel to the end rafter using small sections of the 1" strap.
End Panel
Vertical Frame
Tube for the
End Wall
Main Cover
Strap in D-ring
Top Chord of the
End Rafter
View (above) is from the inside of the shelter looking at the end
panel. Frame and rafter shown differ from actual frame. The
technique used to secure the end panel is the same however. Photo
shows the main cover installed.
END PANEL INSTALLATION