FINAL FRAME INSPECTION FOR COVER
INSTALLATION
Before the cover is installed, complete these steps to
prepare and inspect the frame.
1. Verify that all fasteners are installed and tight.
2. Inspect the frame for fasteners that are installed
in areas where the main cover meets the frame.
Reposition these fasteners (if possible) or wrap
with tarp or duct tape to protect the cover.
3. Inspect all pipe and connections for sharp edges
and file smooth or wrap with tape.
4. Move to
each cable assembly
at the point where
the cables wrap around the rafters and apply the
premium tarp tape over the cables to protect the
main cover once it is installed.
5. Inspect the awning frame to ensure that all Tek
screws are installed as shown in the diagrams.
Verify that no fasteners are in a position to
contact the cover where it wraps around the
awning.
6. Continue with the installation of the main cover.
Required Parts:
• 105383 premium tarp tape
• LJ7510 duct tape
• Metal file to smooth sharp edges
End Rafter Cable Connection
End Wall and Awning Connection
Awning Corner Connection
Examples show connections
wrapped with tarp tape.
Awning Rafter and Rafter Connection
Rafter
Awning
Rafter