KAHUNA
Users Manual
5
INSTALLATION
General Information
1.
Any freight damage must be noted on the freight bill before signing and reported to the
freight carrier with a freight claim established. Identify the components and check for
shortages. If shortages are discovered, contact your distributor immediately.
2.
Consult building owner and / or architect’s plans when applicable to establish the best
lift location. The lift should be located on a relatively level floor with 4 in. minimum
thickness, 3000-psi concrete slab that has been properly cured.
3.
Make sure that the area where the lift will be located is free of obstructions for 12 ft.
above the floor. This includes heaters, building supports, conduits, etc.
4.
Make sure there is adequate space to allow movement around the lift with a vehicle in
place.
Machine Anchoring
1.
Anchors must be installed at least 5-11/16” from any edge or seam in concrete.
2.
The concrete must be at least 4” thick with a compressive strength of 3000psi.
3.
Use a hammer drill with a carbide tip, ¾” diameter solid drill bit. The bit tip diameter
should be to ANSI Standard B95.12-1977 (.775” to .787”).
Fig. 1 Fig. 2 Fig. 3
4.
Keep drill perpendicular to the floor while drilling. Let drill do the work. Drill the hole
completely through the slab or a minimum 5 inches deep. Clean dust from hole. (See
Figure 1)
5.
Using a hammer, carefully tap the anchor bolts into the concrete until the washer rests
against the base plate.(See Figure 2)
6.
Tighten the anchor bolts to 95 to 120 ft-lbs. Do not use an impact wrench on anchor
bolts. (See Figure 3)
Summary of Contents for Kahuna
Page 1: ...OWNERS MANUAL KAHUNA 2009 Chief Automotive Technologies USERS MANUAL ...
Page 2: ......
Page 6: ...KAHUNA Users Manual 4 GENERAL SPECIFICATIONS ...
Page 11: ...KAHUNA Users Manual 9 Controls ...
Page 30: ......
Page 31: ......