7
Table 1 – Operating Weights
50LC**07
UNITS LB (KG)
Base Unit
967 (439)
Economizer
Vertical
75 (34)
Horizontal
122 (55)
Powered Outlet
35 (16)
Curb
14---in/356 mm
143 (65)
24---in/610 mm
245 (111)
Step 2 — Plan for Sequence of Unit Installation
The support method used for this unit will dictate different
sequences for the steps of unit installation. For example,
on curb--mounted units, some accessories must be
installed on the unit before the unit is placed on the curb.
Review the following for recommended sequences for
installation steps.
Curb--mounted Installation —
Install curb
Install field--fabricated ductwork inside curb
Install accessory thru--base service connection package
(affects curb and unit) (refer to accessory installation
instructions for details)
Prepare bottom condensate drain connection to suit
planned condensate line routing (refer to Step 9 for
details)
Rig and place unit
Install outdoor air hood
Install condensate line trap and piping
Make electrical connections
Install other accessories
Pad--mounted Installation —
Prepare pad and unit supports
Check and tighten the bottom condensate drain
connection plug
Rig and place unit
Convert unit to side duct connection arrangement
Install field--fabricated ductwork at unit duct openings
Install outdoor air hood
Install condensate line trap and piping
Make electrical connections
Install other accessories
Frame--mounted installation —
Frame--mounted applications generally follow the
sequence for a curb installation. Adapt as required to
suit specific installation plan.
Step 3 — Inspect unit
Inspect unit for transportation damage. File any claim
with transportation agency.
Confirm before installation of unit that voltage, amperage
and circuit protection requirements listed on unit data
plate agree with power supply provided.
On units with hinged panel option, check to be sure all
latches are snug and in closed position.
Locate the carton containing the outside air hood parts;
see Fig. 9. Do not remove carton until unit has been
rigged and located in final position.
Step 4 — Provide Unit Support
Roof Curb Mount —
Accessory roof curb details and dimensions are shown in
Fig. 5. Assemble and install accessory roof curb in
accordance with instructions shipped with the curb.
NOTE
: The gasketing of the unit to the roof curb is critical
for a watertight seal. Install gasket supplied with the roof
curb as shown in Fig. 5. Improperly applied gasket can also
result in air leaks and poor unit performance.
Curb should be level. This is necessary for unit drain to
function properly. Unit leveling tolerances are shown in
Fig. 4. Refer to Accessory Roof Curb Installation
Instructions for additional information as required.
A-B
0.5” (13)
B-C
1.0” (25)
A-C
1.0” (25)
MAXIMUM ALLOWABLE
DIFFERENCE IN. (MM)
C06110
Fig. 4 -- Unit Leveling Tolerances
Install insulation, cant strips, roofing felt, and counter
flashing as shown.
Ductwork must be attached to curb and
not to the unit. The accessory thru--the--base power and
gas connection package must be installed before the unit
is set on the roof curb.
If electric and control wiring is to be routed through the
basepan, attach the accessory thru--the--base service
connections to the basepan in accordance with the
accessory installation instructions.
Slab Mount (Horizontal Units Only) —
Provide a level concrete slab that extends a minimum of
6 in. (150 mm) beyond unit cabinet. Install a gravel apron
in front of condenser coil air inlet to prevent grass and
foliage from obstructing airflow.
NOTE
: Horizontal units may be installed on a roof curb if
required.
Alternate Unit Support
(In Lieu of Curb or Slab Mount) —
A non--combustible sleeper rail can be used in the unit
curb support area. If sleeper rails cannot be used, support
the long sides of the unit with a minimum of 3 equally
spaced 4--in. x 4--in. (102 mm x 102 mm) pads on each
side.
Summary of Contents for WeatherExpert 50LC
Page 4: ...4 a50 9584 Fig 2 Unit Dimensional Drawing ...
Page 5: ...5 a50 9585 Fig 2 Unit Dimensional Drawing cont ...
Page 14: ...14 a50 9586 Fig 17 50LC 07 Electro mechanical Control Wiring Diagram ...
Page 15: ...15 a50 9592 Fig 18 50LC 07 RTU Open Control Wiring Diagram ...
Page 16: ...16 a50 9587 Fig 19 50LC 07 SystemVut Control Wiring Diagram ...