Gateway (Coordinator) RTU Checklist
Gateway (Coordinator) Installation Checklist
Site
RTU #, Zone Name
Controller ID
Today’s Date
Installer Name
REGEN Energy Operations Center/Support- (949) 258-4415, Option #2
Step
Notes
1
Power off RTU
2
Install Gateway (Coordinator) and components, incl.
wiring. Install Modem Enclosure, wire to Gateway (Coordi-
nator) inside cabinet.
3
Connect test jumper wires: R to lines on relay that will be
connected to original G, Y1, Y2 lines.
4
Glue antenna base, caulk any drilled openings
5
Pause if need to return to previous RTU after
waiting for portal test, note time
Time Paused:
Time Resumed:
6
Power up RTU
7
Confirm modem WAN light is on within one min. After
power up
8
Wait until blower and all stages of cooling are
energized, note any
startup delays
Blower Delay
1
st
stage Delay
2
nd
stage Delay
9
Once all stages of cooling energized, measure
amperage on lines where CTs are clamped,
measure incoming voltage
Incoming Voltage: 277/480/120/208
CT1 Amps:
CT2 Amps:
10
Perform relay test
UP, DOWN, ENTER
Factor in any blower/compressor min. run times and start
delays, note any shutdown delays
Blower Delay:
111
Exit the relay test to start regular operation
12
Confirm READY indicator and at least two bars of signal
strength. Change Zigbee channel if directed by REGEN
support.
UP, DOWN, UP, UP, ENTER
Note time
Channel (
default of 11 or new value
):
# of bars:
13
Move to next RTU, waiting at least 20 min. to
return
14
When you return, power off RTU
15
Remove jumper wires and dress wiring (e.g. tie wraps,
sticky backs)
16
Power up RTU & confirm controller connects to net-
work
(Confirm READY indicator and at least two
bars of signal strength)