To discharge the fodder, you must open the dosing
gate with the auger running and switch on the (option-
al) conveyor belt - if fitted.
1.
Dismiss all persons from the danger area of the
machine.
2.
Keep animals away from the danger area.
3.
Open the block ball valve (1).
Position vertical = open
Position horizontal = closed
4.
Switch the conveyor belt on (see operating man-
ual of the overall plant).
5.
Open the dosing gate (2) (see operating manual
of the overall plant). The set opening width of the
dosing gate is indicated by the position of the in-
dicator (3) on the scale (4).
6.
To end the discharge process:
6.1 Close the dosing gate completely (see op-
erating manual of the overall plant).
6.2 Switch off the conveyor belt if necessary.