8
Inspection and service
Logano plus SB325 – 6 720 806 328 (2013/07)
36
15.
Confirm professional commissioning.
Company stamp/signature/date
Responsive maintenance
Page (individual steps)
Notes
1.
Shutting down the heating system.
Page 31
2.
Clean the combustion chamber.
Page 32
3.
Clean hot gas flues (heating surfaces).
Page 32
4.
Check gaskets on combustion chamber door and replace if
required.
Replace the gaskets on the reversing chamber door and on the
cleaning cover of flue gas collector.
Page 33
5.
Check that the condensate drain pipe is clean and filled with a
hydraulic seal.
6.
Check the neutralising system (where fitted).
See technical documentation of the
neutralising system
7.
Start up the heating system.
Page 28
8.
Final check of the maintenance work, take measurements and
record values and test results.
See technical burner documentation.
9.
Check the safe and proper functioning in operation (safety
equipment).
10.
Confirm professional commissioning.
Company stamp/signature/date
Tab. 17 Heating system maintenance report
Inspection work
Page (individual steps)
Notes
Tab. 16 Inspection report