6
Commissioning
Logano plus SB325 – 6 720 806 328 (2013/07)
30
6.6
Commissioning report
The boiler can be operated with a gas burner.
▶ Carefully complete the commissioning report for the relevant
gas burner.
▶ Sign all completed commissioning work and enter the date.
Commissioning steps
Page
(individual steps)
Comments
(signature)
1.
Flush the heating system.
Page 28
2.
Fill the heating system with water.
Page 29
3.
Vent the heating system.
4.
Carry out tightness test.
Page 21
5.
Switch on the control unit.
▶ Boiler-specific parameters set and recorded.
See technical documentation for the control
unit and specifications, chapter 3.12,
page 12.
6.
Ensure the function of all safety equipment.
7.
Check the fuel line for tightness.
8.
Starting the burner.
See technical burner documentation.
9.
Complete the burner test report regarding the individual
output stages.
10.
Conduct a tightness test on the hot gas side.
After a short time in operation, tighten the screws in the
combustion chamber door to prevent leakage around the
door as a result of the packing cord settling.
11.
Check the flange connections and fitting after the boiler has
been heated up and retighten.
12.
Check flue path for tightness.
13.
Check the flue gas temperature.
14.
Carry out a function test on all safety equipment and record
this.
15.
Instruct the system user and hand over technical
documentation.
16.
Enter the fuel used in the table (
"General" operating
instructions).
17.
Confirm professional commissioning.
Company stamp/signature/date
Tab. 15 Commissioning report