Mounting
The BERT-E has two slotted mounting flanges that may be used for pipe mounting or wall mounting.
Alternatively, the unit may be supported by the conduit using the conduit holes provided.
Refer to
Mounting Dimensions
, page 82 for details.
WARNING
Do not attempt to loosen or remove flange bolts while the meter is
in service.
Cover Jam Screw
The cover jam screw should be properly installed once the meter has been wired and tested in a safe
environment. The cover jam screw is intended to prevent the removal of the meter cover in a flameproof
environment without the use of tools. Using a M2 hex wrench, turn the screw clockwise until the screw
contacts the meter. Turn the screw an additional ¼ to ½ turn to secure the cover. Caution: Excess torque
may damage the threads and/or wrench.
Connections
WARNINGS
Static electricity can damage sensitive components.
Observe safe handling precautions for static-sensitive components.
Use proper grounding procedures/codes.
If the meter is installed in a high voltage environment and a fault or
installation error occurs, high voltage may be present on any lead or
terminal.
To access the connectors, loosen the cover jam screw (if tightened) with an M2 hex wrench, remove the
enclosure cover and unscrew the two captive screws that fasten the display module into the enclosure.
Disconnect the ribbon cable and remove the display module. Power and signal connections are made to
a barrier terminal connector in the base of the enclosure. Grounding connections are made to the two
ground screws provided on the base – one internal and one external. Use proper grounding techniques
for explosion-proof areas and observe all local and national electric codes.
Connections (continued)
S+
Signal input positive terminal connection
S-
Signal input negative terminal connection
COM
DC power supply input return/negative, reset contact closure common
RST
Contact closure reset pull-up to 1.8 VDC
P+
DC Power positive terminal connection (BPD6830AB2B1 only)
LP+
4-20 mA transmitter DC power positive terminal connection.
LP-
4-20 mA transmitter regulated current output terminal connection
OC1+
Open collector output 1 positive terminal
OC1-
Open collector output 1 negative terminal
OC2+
Open collector output 2 positive terminal
OC2-
Open collector output 2 negative terminal
Refer to Figure 1 for terminal positions.
9
Summary of Contents for BERT-E
Page 1: ...Model BERT E Installa on and Opera on Manual BI BERT Revision 01 Engineered for Accuracy...
Page 28: ...26...
Page 38: ...36...
Page 51: ...49...
Page 68: ...66...
Page 70: ...68...
Page 78: ...76...
Page 84: ...Mounting Dimensions All units inches mm Figure 14 Enclosure Dimensions Front View 82...
Page 90: ...This page left blank intentionally 88...
Page 91: ...Notes 89...
Page 92: ...Notes 90...
Page 93: ......