Installation
3.5
Commissioning
Page 24
BOGE Operating instructions for C 10 L...C 20 L series screw compressors
3.5 Commissioning
Check installation
requirements
Caution: Risk of injury!
Prior to any work on the compressor:
–
Switch off the main switch and secure against unintentional switching-on.
–
Check to ensure that all conducting machine parts are voltage free.
–
Depressurize all areas under pressure.
Never omit a single safety step! Otherwise, you will risk injuries due to re-
starting, electric shock or self-releasing parts.
Caution!
With an activated automatic restart (Auto-Restart) the compressor may re-
start automatically after a voltage failure. Prerequisite: The network pressure
is lower than the set cut-in pressure of the operating switch and it was al-
ready switched on before the mains failure – green indicator lamp = ON.
Note!
We recommend the drawing up of a commissioning certificate in which the
test results during the commissioning process can be listed up.
Caution: Risk of injury!
The commissioning may only be carried out by experienced and authorized
qualified personnel!
Always wear protective gloves when working on the compressor to avoid
bruising of fingers or hands while opening or closing components!
Attention!
Make sure that the compressor is installed according to the installation re-
quirements!
List up the test results in the commissioning certificate.