Page 82
GRBL and Universal G
-
code Sender Software
•
Version 1.1e of GRBL has been uploaded to the controller.
•
There are several G
-
code senders for GRBL. I have had success with the Universal G
-
code Sender
Platform Version
•
Some of the firmware values can be changed from the G
-
code sender software. Below is a table for
the default values uploaded into the firmware from GRBL 1.1e.
•
Please see our Q
uick Start guide
for getting started with the drivers and initial settings.
•
Please see our
troubleshooting guide
for getting started with the drivers and initial settings.
Key
Value
Description
$0
5
(Step pulse time, microseconds)
$1
25
(Step idle delay, milliseconds)
$2
0
(Step pulse invert, mask)
$3
0
(Step direction invert, mask)
$4
0
(Invert step enable pin, boolean)
$5
1
(Invert limit pins, boolean)
$6
0
(Invert probe pin, boolean)
$10
1
(Status report options, mask)
$11
0.01
(Junction deviation, millimeters)
$12
0.002
(Arc tolerance, millimeters)
$13
1
(Report in inches, boolean)
$20
1
(Soft limits enable, boolean)
$21
0
(Hard limits enable, boolean)
$22
1
(Homing cycle enable, boolean)
$23
3
(Homing direction invert, mask)
$24
500
(Homing locate feed rate, mm/min)
$25
8000
(Homing search seek rate, mm/min)
$26
250
(Homing switch debounce delay, milliseconds)
$27
5
(Homing switch pull
-
off distance, millimeters)
$30
1000
(Maximum spindle speed, RPM)
$31
0
(Minimum spindle speed, RPM)
$32
0
(Laser
-
mode enable, boolean)
$100
80
(X
-
axis travel resolution, step/mm)
$101
80
(Y axis travel resolution, step/mm)
$102
2267.717
(Z
-
axis travel resolution, step/mm)
$110
10000
(X
-
axis maximum rate, mm/min)
$111
10000
(Y axis maximum rate, mm/min)
$112
500
(Z
-
axis maximum rate, mm/min)
$120
800
(X
-
axis acceleration, mm/sec^2)
$121
800
(Y axis acceleration, mm/sec^2)
$122
300
(Z
-
axis acceleration, mm/sec^2)
$130
450
(X
-
axis maximum travel, millimeters)
$131
390
(Y axis maximum travel, millimeters)
$132
85
(Z
-
axis maximum travel, millimeters)
Summary of Contents for E3
Page 1: ...Page 1 Version 2 15 Assembly Manual E3 ...
Page 21: ...Page 21 Step 5 Attach Y Carriage Bottom Support and secure with five M4 x 16 screws and nuts ...
Page 22: ...Page 22 Step 6 Attach Z Rail Stop and secure with two M4 x 16 screws and nuts ...
Page 31: ...Page 31 Slide 8 x 22 x 7 Bearing on Threaded Rod Thread 5 16 Nut on top of the Bearing ...
Page 37: ...Page 37 Secure Stepper Motor Mount with four M4 x 16 Screws and Nuts ...
Page 45: ...Page 45 1 2 IMPORTANT Note the orientation of the Controller Mount below ...
Page 46: ...Page 46 1 4 Using slots and tabs set the Controller Mount Assembly on the Gantry Frame 1 3 ...
Page 50: ...Page 50 Attach Idler Mount and secure with a M4 x 16 screw and nut Step 4 ...
Page 60: ...Page 60 ...
Page 71: ...Page 71 These photos illustrate how the belt wraps around the GT2 Pulley and Idler ...