Method of Installation
1. Locate and isolate power to distribution panel
where installation is to take place.
2. Identify the single conductor wire to be
monitored and direction of flow/load.
3. Attach the current transformer around
the conductor to be monitored without placing
excessive strain or pressure. Do not route the
leads over sharp edges and take care to fit the
CT with the arrow in direction of flow/load.
Notes:
If you placed the wire in the
wrong terminal, gently press plastic
clip with a screwdriver to release
(as seen in picture above).
If the Analytics platform shows a
negative kW trace, either reverse the
black and white leads or reverse the
direction of current flow through the
CT’s.
4. For greater accuracy of measurement it is
advisable to cable tie the conductor to the
CT body so the conductor passes through
the centre of the CT.
5. Repeat steps 2 to 4 for the other phases to
be measured.
6. Now push the CT secondary leads into the
RJ12 adaptor terminals for your phase
type as shown on the next page. The white
cable of each CT connects to either
terminals 1, 2 and 3 of the side showing the
Best.Energy logo. The corresponding black
cable of each CT connects to terminal of
same number on the opposite side of the
terminal block.
17