04/03
347
LB 444
35
5.3
Electrical Connections
5.3.1
Detector
4
3
2
1
5
LB 440
PA
Pt 100
Switch off the evaluation unit before
connecting the scintillation counter.
Open the screws and remove the con-
nection box cover to expose the connec-
tion area.
With fail-safe installations, connect the
detector to the potential equalization bar
of the installation.
The detector is connected to the evalua-
tion unit via a 2-wire cable with approx.
8…10 mm diameter and a cross-section
of 1 mm
2
. A screen cable may be used
in installations with extremely strong
electrical interferences. The screen may
be placed only on one side of the detec-
tor.
Figure 20:
Cable connections at detector
In fail-safe installations the permissible inductivities and capacities of the con-
nection cable have to be observed in accordance with the Ex test certificate.
Please observe the maximum cable lengths between evaluation unit and detector (see
chapter 9 TECHNICAL DATA.
When installing the connection cable, make sure that water cannot get into the connec-
tion box via the cable. With ambient temperatures >70°C, the installed cable has to be
protected to prevent exceeding of the temperature limits of the cable. Following connec-
tion, check that the connection box is carefully closed and the cable bushing properly
sealed.
If a resistance thermometer is connected, the cables coming from the
Pt 100
are passed
through the second cable bushing to terminals
3
and
4
.
For equipment installed in the Ex-area, please observe the special requirements
for the cable and the preparation of the connection wires.
The detector LB 44... has to be used for installation in the Ex-area. The detector
LB 54.. may only be used for non Ex-applications.
The evaluation unit must always be installed outside the Ex-area.
A special transmission technique ensures interference suppression. Nevertheless, the ca-
ble should not be installed together with power cables.
Summary of Contents for LB 444
Page 1: ...Density Meter LB 444 Id No 32816BA2 Rev No 04 22 04 03 ...
Page 2: ......
Page 9: ...04 03 347 LB 444 VII ...
Page 10: ......
Page 109: ...04 03 347 LB 444 99 13 4 Mounting Device 90 for Pipe Diameter 21 3 76 1 mm ...
Page 112: ...04 03 347 LB 444 102 ...
Page 113: ...04 03 347 LB 444 103 ...
Page 114: ...04 03 347 LB 444 104 ...
Page 117: ...04 03 347 LB 444 1 14 Ex Certificates for Evaluation Unit ...
Page 118: ...04 03 347 LB 444 2 ...
Page 119: ...04 03 347 LB 444 3 ...
Page 120: ...04 03 347 LB 444 4 15 Ex Certificate for the Detectors ...
Page 121: ...04 03 347 LB 444 5 ...
Page 122: ...04 03 347 LB 444 6 ...
Page 123: ...04 03 347 LB 444 7 ...
Page 124: ...04 03 347 LB 444 8 ...