Commissioning/Configuration
EP5xxx
77
Version: 2.3.0
4.6.1.3
EP5101-2011 - PDO assignment
Fig. 68: PDO assignment and content, EP5101-2011
PDO Assignment
To configure the process data, select the required Sync Manager (SM 2 or SM 3 can be changed) in the
Sync Manager
field at the top left (see illustration above). The process data assigned to this Sync Manager
can then be switched on or off in the
PDO Assignment
field below. Restarting the EtherCAT system, or
reloading the configuration in configuration mode (F4), causes the EtherCAT communication to restart, and
the process data is transferred from the terminal.