Slider Brackets
Figure 32. X-Tension median installation.
Post 5 Shear Bolts
Median Radius Rail
Impact Head
Median Impact Head
This section deals with installation of a X-Tension Median Attenuator System (X-MAS) as a median
guardrail terminal end application.
Site preparation
The X-Tension Median Attenuator System is installed parallel to the standard median barrier,
therefore no offset is used (Figure 32).
Ensure that the area where the X-Tension is to be installed is flat enough so that the soil anchor
will not protrude more than 100mm (4 in) [preferred 75 mm 3 in)] from ground level when
measured with a straight line over a 1.5m (5 ft) cord. Minor site grading may be required.
X-MAS - Median Installation Instructions
X-TENSION
®
SYSTEM