Appendix A. CE Mark compliance and high noise
environments
A.1 Introduction
For CE Mark compliance, the
PanaFlow Z1G/Z2G Process Gas
Flowmeter
must meet the EMC and LVD directives.
Attention European Customers!
CE Mark compliance is required for all units
intended for use in EU countries, and it is
also recommended for installation in high
electrical noise environments.
A.2 EMC compliance
In addition to the standard wiring requirements, the
electrical connections must be shielded and grounded as
described in
Table 11
below for EMC compliance. After all the
necessary electrical connections have been made, seal any
unused cable entry holes.
Note:
If the instructions in this appendix are followed, the
unit will comply with the EMC Directive.
Table 11: Wiring modifications
Connection Cable Type
Termination
Modification
Transducer Shielded Cable
Terminate the shield
using the cable glands
(already done).
Power
Shielded Cable
Terminate the shield
using the cable glands.
Shielding
Wires enclosed in a properly-grounded
metal conduit do not require additional
shielding.
All Input
/ Output
Options
Shielded Cable
IMPORTANT:
Make sure to connect the PanaFlow Z1G/Z2G Process Gas
Flowmeter case to the earth ground with a grounding
cable, using the external ground screws found on either
side of the enclosure. The connection should be less than
9.8 feet (3 meters) long.
31
Summary of Contents for PanaFlow Z1G
Page 1: ...PanaFlow Z1G Z2G User s manual 910 321 Rev A...
Page 2: ...ii...
Page 4: ...no content intended for this page iv...
Page 9: ...no content intended for this page 1...
Page 21: ...Figure 12 Remote mount electronics transducer and preamplifier wiring ref dwg 702 731 732 13...
Page 28: ...no content intended for this page 20...
Page 30: ...no content intended for this page 22...
Page 38: ...no content intended for this page 30...
Page 40: ...no content intended for this page 32...
Page 43: ...Table 13 Service record cont Date Description of service Performed by 35...