x24
1-1/2" (3,8 cm)
x2
2 x 4 x 24" (5,1 x 10,2 x 61 cm)
RL
TEMPORARY SUPPORT
x2
2 x 3 x 75-1/4" (5,1 x 7,6 x 191,1 cm)
ECA
28
GABLE PANELS
PARTS REQUIRED:
x2
x2
x2
Primed
side up
Primed
side up
Primed
side up
1-3/4"
(4,5 cm)
1-1/2"
(3,8 cm)
1-1/2"
(3,8 cm)
1-1/2"
(3,8 cm)
Nails
RL (on flat)
RL
RL
RL
ECA
ECA
You will build
TWO
assemblies. Orient
RL
and
ECA
on flat as shown.
Place LEFT front gable panel as shown and secure using 1-1/2" nails.
2
1
BEGIN
3
4
5
Place MIDDLE front gable panel flush to installed left panel. Ensure panels are flush.
Secure panel to installed
RL
using 1-1/2" nails. Place second
RL
as shown under MIDDLE panel and secure using
1-1/2" nails.
Place RIGHT front gable panel flush to installed middle panel. Ensure panels are flush.
Secure to
RL
using 1-1/2" nails.
Repeat
Steps 1-4
to build second gable panel.
You have finished assembling your gable panels.
FINISH
6
Flush
Flush
Maintain
Flush
Maintain
Flush
1-3/4"
(4,5 cm)
1-1/2"
(3,8 cm)
Nails
1-1/2" (3,8 cm)
Nails