background image

4

RIGGING

1. To simplify rigging and installation, units are shipped in one

piece, so only one lift is required. It is important to follow the
guidelines listed below when rigging these units.

2. Lifting devices have been provided for short lifts and final

positioning. The table “Approximate shipping weights” on page 7
shows the location of the lifting devices for each tank size. For
safety, it is recommended that for extended lifts or whenever
hazards exist, safety slings are used in addition to the spreader
beams.

3. Lifting and transportation of the equipment by means of lift

trucks is not permitted, as this may result in serious damage of
the tank bottom and the ice coils.

4. Spreader bars of the full width of the section must be used

between the lifting cables to prevent damage to the section. 
For extended lifts or where hazards exist, it is recommended to
use the lifting devices in conjunction with safety slings placed
under the unit.

ON A LEVEL CONCRETE PAD

The unit should be continuously supported on a level concrete pad.
After the unit is set into final position, the tank bottom should be
sealed airtight all around to prevent condensation formation (see
figure). The sealer is shipped loose with the unit, together with the
air pump.

 1. Seal around base of tank

ON 3 I-BEAMS

If continuous support is not possible, an alternative recommended
support arrangement consists of 3 parallel I-beams extending the
full length of the unit: 2 supporting beams should be located along
the unit length and 1 beam should be located on the centreline of
the unit. (see figure)
Each beam should be sized for 65% of the total operating weight. If
a unit is installed on I-beams additional insulation of the tank
bottom is necessary to avoid the formation of condensation.

ON A ROOF

For installation of the unit on a roof, additional field insulation
between tank bottom and the roof is required to prevent
condensation formation on the ceiling of the floor below (see
figure). Recommended insulation material is a vapour tight cork
layer.

 1. Cork layer

General Notes

Support requirements

Figure 1: Unit continuously supported on a level concrete pad

Figure 2: Installation on 3 I-beams

Figure 3: Installation on the roof

Summary of Contents for Ice Chiller TSC-1050C

Page 1: ...nd to assure that all necessary equipment will be available at the jobsite Be sure to have a copy of the unit certified drawing available for reference If you do not have a copy of this drawing or if...

Page 2: ...lifting when available hoisting capacity provides little margin for safety Before an actual lift is undertaken ensure no water snow ice or debris has collected in the sump or elsewhere in the unit Su...

Page 3: ...g on operating equipment be aware that some parts may have an elevated temperature Any operations on elevated level have to be executed with extra care to prevent accidents Air piping between air pump...

Page 4: ...pported on a level concrete pad After the unit is set into final position the tank bottom should be sealed airtight all around to prevent condensation formation see figure The sealer is shipped loose...

Page 5: ...ifting methods not permitted Model TSU C D L x W Dimensions Approx Shipping weight kg A mm B mm C mm TSU 95C TSU 115C 3073 x 1308 3683 x 1308 2550 2780 1597 2403 738 640 1124 1124 TSU 120C TSU 145C TS...

Page 6: ...on and corrosion REFRIGERANT CONNECTIONS ON SITE All connections in the external pipework installed by others must be leak free and tested accordingly All piping external to BAC cooling equipment must...

Page 7: ...local BAC representative 1 Non return valve 2 Steel pipe for initial 3m then PVC for remainder of air supply by others 3 Filter 4 Air pump Whenever TSC coils are to be installed in a concrete tank the...

Page 8: ...in the Operating and Maintenance Manual see Table Recommended Maintenance and Monitoring Schedule Start up must be performed Proper start up procedures and scheduled periodic maintenance will prolong...

Page 9: ...NOTES 9...

Page 10: ...10 NOTES...

Page 11: ...NOTES 11...

Page 12: ...intervals are for typical installations Different environmental conditions may dictate more frequent servicing 3 When operating in ambient temperatures below freezing the unit should be inspected mor...

Reviews: