Installing S6x00 Hardware
26 Installing the S6200, S6500, and S6800 Conferencing Server
Extend the cable-management arm and fasten
the cables:
Attention: Make sure that you route Fibre
Channel cables through the tab _1_, to ensure
proper bend radius and prevent damage to
these cables.
Extend the cable-management arm by sliding
the server toward the front of the rack. The
rail-lock pins stop the server halfway along the
rack. Secure the cables by using the straps that
are attached to the cable-management arm.
Slide the server back into the rack cabinet.
If you have installed a second power supply in
your server, use the Y-power cable that came
with the power supply option to ensure server
redundancy. Cable your servers as shown,
using one Y-power cable to provide power to
two different servers. Each Y-power cable must
be connected to a different power source, such
as a power distribution unit (PDU), to maintain
redundancy.