6 Operation
6.1 Tests before each operation
1. Make sure that minimal to no vibra-
tions, e.g. from the fluid pump, are
transmitted to the entire system.
2. For electrically conductive fill heads,
check that the entire system is ground-
ed. The grounding of the fill head is
done via the ground wire with the
clamp. The ground wire with the termi-
nal must be free of corrosion.
»
Follow the ATEX and OSHA instruc-
tions and regulations.
Operation
3. Make sure that the fill head is correctly
mounted.
4. For fill heads with plug valve, ball
valve or outlet tap, open the manual
shut-off valve as soon as the system
is connected.
5. Operation can be started.