SG-B SERIES STEAM GENERATOR
E005-28-10-12 9
Fig-7
char t - 6
Model
A
B
C
OC- 30B~0C- 60B
215
215
275
OC- 70B~OC- 120B
215
215
315
OC- 135B~OC- 180B
215
215
405
Water and steam connection
a.
The water supply pipe and steam pipe should comply with local standards
b.
Connect the water inlet valve of the generator to the 15mm mains water supply using a flexible hose
with 1/2 inch fittings.
c.
Steam outlet (1/2 inch or 3/4 inch) use the same dimension copper pipe to connect it, if the steam pipe
is longer than 5 meter it should be insulated. During use the steam pipe will be very hot and must be
protected against accidental contact. Note that according to the location it may be necessary to attach an
additional length of pipe to the pressure relief valve in order to divert the steam flow to a safe direction
should the valve operate.
valve
wate r le ve l p ro b e
S TE A M G E NE RATO R
the s team noz z le
s hould be
mm high
away form the ground in
order to let the bather more
c omfortable the steam noz z le
s hould be ins talled in the plac e
whic h is far from the s eat
300
,
overheat swit ch
(Fig-8)
d.
Connect the drain outlet to a suitable drain via a copper pipe with the appropriate fittings.
e.
Make a secure connection between steam nozzle & steam pipe.
f.
Use non corrosive hose with
½
inch unions to connect between the descaling liquid container and the
inlet valve; note the descaling liquid container must be mounted at least 500 mm above the steam
generator.
Installation for controller and temperature probe.
OC-B controller is water proof and can be installed inside or outside the steam room according to customer
preference.
(1) Ideally the control panel should be installed at a height of approximately 1200mm for ease of use.
(2) Installation method: drill a
Φ
40mm hole on wall. open the front cover of steam generator .pin the
control cable (6 cores) and temperature sensor cable (2 cores) to the relevant ports . put the protuberant
back of controller in the hole the bottom of controller press close to the wall .then fix it and cover the cover.
(3) Control panel installation: pin one end to circuit board ports in steam generator connect the other end
to the controller's cable.
Summary of Contents for OC-105B
Page 1: ......