Base with frame
Lift the base with frame into place on the concreted foundation, that is fitted with bond plates. Bring the base
into the level position.
To ensure the proper operation of the dryer, use a water level to verify that the top surface of the base is abso-
lutely
level
before continuing the installation work.
To ensure that the unit will remain upright even if the wind strong, attach its legs by welding to the bond plates in
the concreted foundation or fix them by means of expansion anchors (4 pcs./M16).
Sections, air channel ends
The sections are delivered ready-assembled including the air channel ends. The air channel ends of the export
model are delivered in parts. The air channel ends can be assembled and attached to the sections while still on
the ground. Provide each joint with a sealing strip.
While lifting the sections into place, make sure that they come in the right way. The inlet side of the sections shall
come on the trough-rod side of the base.
For proper operation of the dryer it is essential that the air inside the triangular channels of the sections flows in
the correct direction: the open end of the triangular channel halves shall be come on the section's inlet side (fac-
ing to the heater).
Before lifting the lowest section into place, affix self-adhesive sealing strips to the upper surfaces of the base.
Place the strip on the inner edge of the horizontal contact surfaces of the base and the section. Provide all the
joints with seals.
When inserting bolts into the holes in the joints between the sections, put also the fixing irons for the ladder A73310
into place. See their installation position in the principle drawings for the dryer. Place the irons at every other joint.
Use M10x20 bolts for joining together the corner reinforcement legs of the sections and the top tanks.
NOTE!
Remove the lifting lugs (501010) as soon as the sections are in place!
Top tanks and cover with handrails
Place a sealing strip on the inner edge of the horizontal contact surfaces of the top tank. Provide all the joints with
seals.
When inserting bolts into the holes in the top tank joints, put also the fixing irons for the ladder A73310 into place.
See their installation position in the principle drawings for the dryer. Place the irons at every other joint.. Continues
following the distribution on the section. Use M10x20 bolts for joining together the corner reinforcement legs of
the sections and the top tanks.
The top tanks and the sections can all be joined together while still on the ground, and lifted up in one go. NOTE!
Observe the weight.
Summary of Contents for Vacboost M13
Page 17: ...Antti Teollisuus Oy 17 408111 03 2019 Vacboost M13 C 255 C 255_malli ...
Page 18: ...Antti Teollisuus Oy 18 408111 03 2019 Vacboost M13 C 320 C 320_malli ...
Page 19: ...Antti Teollisuus Oy 19 408111 03 2019 Vacboost M13 C 365 C 365_malli ...
Page 20: ...Antti Teollisuus Oy 20 408111 03 2019 Vacboost M13 C365 E A1500_3D C365 E A1500 ...
Page 21: ...Antti Teollisuus Oy 21 408111 03 2019 Vacboost M13 C 410 E 700_3D C410 E 700 ...
Page 22: ...Antti Teollisuus Oy 22 408111 03 2019 Vacboost M13 C410 E 1000_3D C410 E 1000 ...
Page 23: ...Antti Teollisuus Oy 23 408111 03 2019 Vacboost M13 C 410 E A1500_3D C410 E A1500 ...
Page 25: ...Antti Teollisuus Oy 25 408111 03 2019 Vacboost M13 ...
Page 32: ...Antti Teollisuus Oy 32 408111 03 2019 Vacboost M13 C365 uunin putket Heater pipes C365 ...
Page 33: ...Antti Teollisuus Oy 33 408111 03 2019 Vacboost M13 D800 putket D800 pipes ...
Page 35: ...Antti Teollisuus Oy 35 408111 03 2019 Vacboost M13 Puhallinteline asentaminen ...
Page 64: ...Antti Teollisuus Oy 64 408111 03 2019 Vacboost M13 ...